Perpetua Resources Corp. press release
NovaCopper Announces Positive Preliminary Economic Assessment for the Arctic Open-Pit Polymetallic Project
NASDAQ - Nasdaq Stock Market · Gold · Antimony · Silver · United States
##
Estimated pre-tax NPV8%of $928 millionand 23% IRR for the Project at base case long term metal prices
TSX, NYSE-MKT Symbol: NCQ
VANCOUVER, July 30, 2013/CNW/ - NovaCopper Inc. (TSX, NYSE-MKT: NCQ) ("NovaCopper" or the "Company") is pleased to announce the positive results of its independent National Instrument 43-101-compliant Preliminary Economic Assessment ("PEA") for its Arctic Copper-Zinc-Lead-Silver-Gold Project (the "Project") in the Ambler mining district of Northwestern Alaska. The PEA was prepared by Tetra Tech of Vancouver, Canadaand the full technical report will be filed on SEDAR and EDGAR within 45 days of this news release. The PEA describes the potential technical and economic viability of establishing a conventional open-pit copper-zinc-lead-silver-gold mine-and-mill complex for the Project. The base case scenario utilizes long-term metal prices of $2.90/lb for copper, $0.85/lb for zinc, $0.90/lb for lead, $22.70/oz for silver and $1,300/oz for gold. The PEA was prepared on a 100% ownership basis and all amounts are stated in U.S. dollars unless otherwise noted.
Highlights of the PEAstudy are as follows:
Initial capital expenditure of $717.7 millionand sustaining capital of $164.4for total estimated capital expenditures of $882.1 millionover the estimated 12-year mine life. In addition, closure and reclamation costs are estimated at $81.6 million. Pre-tax Net Present Value (NPV)8%of $927.7 millioncalculated at the beginning of the two-year construction period and an Internal Rate of Return ("IRR") of 22.8% for the base case. After-tax NPV8%of $537.2 millionand after-tax IRR of 17.9% for the base case. Estimated, pre-tax, payback of initial capital in 4.6 years and 5.0 years after-tax. Minimum 12-year mine life supporting a maximum 10,000 tonne-per-day conventional grinding mill-and-flotation circuit to produce copper, zinc and lead concentrates containing significant gold and silver by-products. Life of mine strip ratio of 8.39 to 1. Average annual payable production projected to be 125 million pounds of copper, 152 million pounds of zinc, 24 million pounds of lead, 29,000 ounces of gold and 2.5 million ounces of silver for life of mine. On a copper equivalent basis, equates to 210 million pounds of copper per year. A capital intensity ratio on initial capital of $6,995per tonne of average annual copper produced. Estimated cash costs of $0.62/lb of payable copper (C1 cash costs include on-site mining and processing costs, road tolls, transport, royalties and is net of by-product credits). Total "all-in" cash costs (initial/sustaining capital, operating, transportation, treatment and refining charges, road toll, and by-product metal credits) estimated at $1.26/lb of payable copper. Economic indicators justify moving forward with a pre-feasibility study.
The PEA should not be considered to be a pre-feasibility or feasibility study, as the economics and technical viability of the Project has not been demonstrated at this time. The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. Furthermore, there is no certainty that the PEA will be realized.
NovaCopper will host a conference call on Tuesday, July 30, 2013at 8:00am (Pacific Time) or 11:00am (Eastern Time) to discuss these results. Call-in information is provided at the end of this news release.
"The results of the PEA show that the Arctic Deposit has positive economics even in today's low metal price environment. The Project has excellent margins with annual average payable production of approximately 125 million pounds of copper at an average cash cost of $0.62per pound of copper net of by-product credits. On that basis, once in production as contemplated by the PEA, Arctic would be in the lowest quartile among copper producers in terms of cash costs." said Rick VanNieuwenhuyse, NovaCopper's President and Chief Executive Officer. "While the economics of the Project are positive, I believe that some of the Project parameters, such as metallurgical recoveries, capital and operating costs, can be improved, and we will continue to focus on these aspects going forward. We are looking forward to working with the Alaska Industrial Development Export Authority ("AIDEA") to advance the Arctic Project and bring significant economic benefits to the people of the Northwest Arctic Borough and the people of Alaska. AIDEA is the lead proponent for the permitting, financing and construction of an industrial access road to the Ambler mining district and the completion of this PEA provides further impetus for AIDEA to move forward on the permitting and construction of the Ambler access road."
"The Arctic Project is advancing at a time of ever increasing resource nationalism, particularly prevalent in major copper producing regions in the world," added Mr. Van Nieuwenhuyse. "I believe that NovaCopper's time-tested relationship with Alaska's major stakeholders in the Project, the Native Corporations as well as the Government of Alaska, will serve as a sound foundation for a stable long-term economic development in this important region."
Preliminary Economic Assessment - Mining and Processing:
The PEA is based on a conventional truck-and-shovel, open-pit mine design at a single pit with milling and sulphide concentration resulting in the production of copper, zinc and lead concentrates. Based on the preliminary metallurgical work on the sulphide mineralization, the average recoveries are projected to be 87.1% for copper, 86.8% for zinc, 74.0% for lead, 80.4% for silver and 64.7% for gold. The mineralized material at the Project will be processed through conventional milling and flotation for an estimated mine life of 12 years. The PEA contemplates the metallurgical flow sheet to consist of a conventional mill with a talc pre-float followed by a bulk copper-lead flotation and zinc flotation followed by a separation of the copper and lead. Most of the precious metals will report to the copper and lead concentrates. Total processing is based on a 10,000 tonne-per-day operation. Key parameters and assumptions used for the PEA study are discussed below and summarized in Tables 1 through 3on the following pages.
Table 1 - Mining rates and volumes of mined material
| Type of Mining | Total Years | Avg Tonnes/yr (000's) | Avg Tonnes/day | Total Tonnes (000's) | | Open-pit mineralized material (Years 0 - 12) | 12 | 2,973 | 8,146 | 35,681 | | Open-pit waste (Years 0 - 12) | 12 | 24,946 | 68,346 | 299,354 | | | | | | | | Total material mined | 335,036 | | | | | Average strip ratio for the life of mine | 8.39:1 | | | |
Table 2 - Projected payable metal production
| Metal | Total Payable Production | Average Annual Production Life of Mine | | | | | lbs (000's) | Tonnes | lbs (000's) | Tonnes | | Copper | 1,500,678 | 680,696 | 125,056 | 56,725 | | Zinc | 1,821,895 | 826,398 | 151,825 | 68,866 | | Lead | 289,246 | 131,200 | 24,104 | 10,933 | | | Ounces | Ounces | | | | Silver | 30,491,812 | 2,540,984 | | | | Gold | 349,094 | 29,091 | | |
Table 3 - Base case head grades, recoveries, metal prices, and other data
| | | | | | | | | | | | | | | | | | | | | | | | | | | | Head Grades | | | | | | | | | | | | | | | | | | | | | | | | | | | Copper | | | | | | | | | | | % | | | | | | | | | | | | | | 2.28 | | Zinc | | | | | | | | | | | % | | | | | | | | | | | | | | 3.13 | | Lead | | | | | | | | | | | % | | | | | | | | | | | | | | 0.53 | | Silver | | | | | | | | | | | g/t | | | | | | | | | | | | | | 36.91 | | Gold | | | | | | | | | | | g/t | | | | | | | | | | | | | | 0.50 | | Metal Recoveries | | | | | | | | | | | | | | | | | | | | | | | | | | | To Copper Concentrate | | | | | | | | | | | | | | | | | | | | | | | | | | | - Copper | | | | | | | | | | | % | | | | | | | | | | | | | | 87.1 | | - Silver | | | | | | | | | | | % | | | | | | | | | | | | | | 40.2 | | - Gold | | | | | | | | | | | % | | | | | | | | | | | | | | 57.9 | | To Zinc Concentrate | | | | | | | | | | | | | | | | | | | | | | | | | | | - Zinc | | | | | | | | | | | % | | | | | | | | | | | | | | 86.8 | | To Lead Concentrate | | | | | | | | | | | | | | | | | | | | | | | | | | | - Lead | | | | | | | | | | | % | | | | | | | | | | | | | | 74.0 | | - Silver | | | | | | | | | | | % | | | | | | | | | | | | | | 40.2 | | - Gold | | | | | | | | | | | % | | | | | | | | | | | | | | 6.8 | | Payables | | | | | | | | | | | | | | | | | | | | | | | | | | | Payable Copper | | | | | | | | | | | % | | | | | | | | | | | | | | 96.55 | | Payable Zinc | | | | | | | | | | | % | | | | | | | | | | | | | | 85.71 | | Payable Lead | | | | | | | | | | | % | | | | | | | | | | | | | | 94.00 | | Payable Silver | | | | | | | | | | | % | | | | | | | | | | | | | | 90 | | Payable Gold | | | | | | | | | | | % | | | | | | | | | | | | | | 95 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Table 3 Continued - Base case head grades, recoveries, metal prices, and other data
| | | | | | | | | Concentrate grades - Copper | | | | | | | | Copper | | | % | | | 29.0 | | Silver | | | g/t | | | 217 | | Gold | | | g/t | | | 4.2 | | Concentrate grades - Zinc | | | | | | | | Zinc | | | % | | | 56.0 | | Concentrate grades - Lead | | | | | | | | Lead | | | % | | | 50.0 | | Silver | | | g/t | | | 1,887 | | Gold | | | g/t | | | 4.3 | | Metal Prices | | | | | | | | Copper | | | $/lb | | | 2.90 | | Zinc | | | $/lb | | | 0.85 | | Lead | | | $/lb | | | 0.90 | | Silver | | | $/oz | | | 22.70 | | Gold | | | $/oz | | | 1,300 | | Other Parameters | | | | | | | | Life of mine | | | Years | | | 12 | | Fuel price | | | $/l | | | 1.182 | | Electrical power - diesel generators | | | $/kWhr | | | 0.322 | | NANA NSR | | | % Net Revenues | | | 1.0 | | | | | | | | | | | | | | | | |
Preliminary Economic Assessment - Project Economics:
The results of a discounted cash flow analysis for the Project are presented in Table 4below. NPV, IRR and payback values are estimated for both pre-tax and after-tax scenarios. The base case scenario utilizes the long-term metals prices outlined in Table 3and a discount rate of 8%. IRR and NPV values are calculated for a range of copper prices from $2.50 to $3.50.
Under the Exploration Agreement and Option to Lease ("NANA Agreement") between NovaCopper and NANA Regional Corporation, Inc. ("NANA"), NANA has the right, following a construction decision, to elect to purchase a 16% to 25% direct interest in the Project or, alternatively, to receive a 15% Net Proceeds Royalty ("NPR"). This PEA was carried out on a 100% ownership basis and does not include the impact on NovaCopper if NANA elects to purchase an interest in the Project under the NANA Agreement or, alternatively, the impact on NovaCopper and the Project if the NPR becomes applicable. The PEA does include the 1.0% Net Smelter Royalty ("NSR") to be granted to NANA under the NANA Agreement in exchange for a surface use agreement. Additional information on the NANA Agreement is included in NovaCopper's 2012 Annual Report on Form 10-K, which contains a detailed discussion of the NANA Agreement, and is available on SEDAR and EDGAR.
Table 4 - Pre-tax discounted cash flow estimates for varying copper prices
| Pre-Tax NPV* ($ million) | Copper Price ($/lb) | | | | | | | 2.50 | 2.75 | Base Case 2.90 | 3.25 | 3.50 | | | | Discount rates | 5% | 963.1 | 1,206.7 | 1,352.9 | 1,694.0 | 1,937.7 | | Base Case 8% | 618.9 | 811.9 | 927.7 | 1,198.0 | 1,391.0 | | | 10% | 443.7 | 610.2 | 710.1 | 943.2 | 1,109.7 | | | | | | | | | | | IRR | % | 18.5 | 21.2 | 22.8 | 26.3 | 28.7 | | Payback | Years | 5.1 | 4.8 | 4.6 | 4.3 | 4.1 |
*Assumes base case metals prices of $0.85/lb zinc, $0.90/lb lead, $22.70/oz silver and $1,300/oz gold
Table 4 Continued - After-tax discounted cash flow estimates for varying copper prices
| After-Tax NPV* ($ million) | Copper Price ($/lb) | | | | | | | 2.50 | 2.75 | Base Case 2.90 | 3.25 | 3.50 | | | | Discount Rates | 5% | 562.2 | 738.5 | 844.2 | 1,083.5 | 1,246.1 | | Base Case 8% | 312.4 | 453.0 | 537.2 | 727.6 | 857.3 | | | 10% | 186.0 | 307.7 | 380.6 | 545.4 | 657.8 | | | | | | | | | | | IRR | % | 14.0 | 16.5 | 17.9 | 20.9 | 22.9 | | Payback | Years | 5.6 | 5.2 | 5.0 | 4.6 | 4.4 |
*Assumes base case metals prices of $0.85/lb zinc, $0.90/lb lead, $22.70/oz silver and $1,300/oz gold
As seen in Table 5, average life of mine cash costs for the Project, which include on-site operating costs, treatment and refinement charges, transportation, road toll charges, royalties and by-product credits (zinc, lead, silver and gold), are estimated to be $0.62/lb of payable copper. If the total capital costs (initial plus sustaining and closure costs) of $963.7 millionare included, then the total "all-in" cash cost is estimated to be $1.26/lb of payable copper.
Table 5 - Summary of estimated cash costs
| Cash Costs ($/lb Cu payable) | Average Life of Mine | | C1 (delivered metal - net of by-product credits) | 0.62 | | Total Cash Costs (opex, TC/RCs, capex, sustaining capex, closure) | 1.26 |
This PEA was developed on the basis of up-to-date macro-economic and technical assumptions related to the Arctic Project and supersedes the previous PEA completed in 2011.
Capital Costs
The PEA estimates the initial development capital expenditure at $717.7 millionduring the proposed two-year construction period. With sustaining (deferred and working) capital over the life of the mine estimated at $164.4 million, the expected total capital investment is expected to be $882.1 millionover the estimated 12-year mine life. In addition, closure costs are estimated to be $81.6 million. All estimates, which are shown in Table 6, are based on budget quotations and Tetra Tech's database/experience with similar projects and are not definitive estimates based on vendor quotations.
Table 6 - Capital estimate summary
| Initial Capital Estimate ($ million) | | | Overall Site | 82.5 | | Open Pit Mining | 119.7 | | Mineralized Material Handling | 17.4 | | Process Plant | 122.2 | | Tailings and Water Management | 21.0 | | On Site Infrastructure | 49.1 | | Airstrip | 14.2 | | External Access Roads | 27.2 | | Temporary Services | 23.1 | | Subtotal | 476.4 | | Indirect Costs | 130.9 | | Owner's Costs | 18.6 | | Contingency | 91.9 | | Initial development capital | 717.7 | | Sustaining Capital Estimate ($ million) | | | Mining Equipment | 45.6 | | Tailings | 112.8 | | Other Equipment | 6.0 | | Total sustaining capital | 164.4 | | Total capital expenditure for the life of mine | 882.1 |
Rounding as required by reporting guidelines may result in apparent summation differences
Infrastructure
The Arctic Project will require 15 MW of peak load for 10,000 tonne-per-day operation demand. Power will be generated by five self-contained 3.6 MW prime diesel generators. Four units will be in service with the fifth unit reserved for maintenance. Onsite power costs using diesel are estimated to be $0.322/kWh, assuming a diesel price of $1.182/l.
There is currently no developed surface access to the Project area. Access to the Project is proposed to be via a road approximately 340 km (211 miles) long, extending west from the Dalton Highway where it would connect with the proposed Project area. Although the capital costs of the road are not yet known, NovaCopper has been in discussions with ADIEA. The working assumption in this PEA study is that AIDEA would arrange financing in the form of a public-private partnership to construct and arrange for the construction and maintenance of the access road. AIDEA would charge a toll to multiple mining and industrial users (including NovaCopper's Arctic Project) in order to pay back the costs of financing the AMDIAR. This model is very similar to what AIDEA undertook when the Red Dog Road and Port facilities were constructed during the 1980s. The amount paid in tolls by any user will be affected by the cost of the road, its financing structure, and the number of mines that would use the AMDIAR to ship concentrates to a port in Alaska. For the purposes of this PEA study it has been assumed that a toll would be paid based on a $150-million30-year bond at a 5% interest rate, which would result in the Arctic Open Pit Project paying approximately $9.7 millioneach year for its 12-year mine life. The toll payments are assumed in the PEA to commence when the Project has reached commercial production.
Operating Costs
The Project is projected to produce approximately 125 million pounds of payable copper per year at an estimated average C1 cash operating cost of $0.62/lb Cu over the estimated 12-year mine life. These estimated cash costs are net of zinc, lead, gold and silver byproducts and include onsite operating costs, transport, road tolling, smelting and refining charges and royalties. Maintenance parts and repairs are estimated based on industry standard factors for these costs. Mining costs are estimated at $3.02per tonne of material mined, at a strip ratio of 8.39 which equates to $28.40per tonne of material processed. Details of the estimated operating costs, and other charges, are presented in Tables 7 and8below.
Table 7 - Operating costs
| | | | | | | | | | | Estimated Operating Cost (as indicated) | | | | | | | | | | Mining | | | | $/tonne processed | | | | 28.40 | | Processing | | | | $/tonne processed | | | | 19.86 | | General and Administrative | | | | $/tonne processed | | | | 8.92 | | Plant Services | | | | $/tonne processed | | | | 3.48 | | Road Toll | | | | $/tonne processed | | | | 3.27 | | Total on-site operating costs | | | | $/tonne processed | | | | 63.91 | | | | | | | | | | | | | | | | | | | | |
Table 8 - Concentrate transportation, treatment and refining charges
| | | | | | Estimated Operating Cost (as indicated) | | | | | Concentrate Transportation charges | | $/wmt concentrate | 147.98 | | Treatment charges - Copper | | $/dmt concentrate | 70.00 | | Treatment charges - Zinc | | $/dmt concentrate | 260.00 | | Treatment charges - Lead | | $/dmt concentrate | 180.00 | | Refinement charges - Copper | | $/lb of payable copper | 0.07 | | Refinement charges - Silver | | $/oz of payable silver | 0.60 | | Refinement charges - Gold | | $/oz of payable gold | 10.00 |
wmt: wet metric tonne dmt: dry metric tonne
Mineral Resource Estimate
The mineral resource estimate, as seen in Table 9 and which formed the basis of the PEA, was completed by Mr. MichaelF. O'Brien, M.Sc., Pr.Sci.Nat, FGSSA, FAusIMM, FSAIMM and an independent Qualified Person as set forth by National Instrument 43-101. The overall effective date of this resource estimate is July 30, 2013. The mineral resource estimate prepared by Tetra Tech considers diamond drill holes drilled by different operators during the period 1965 to 2011. The majority of the drilling has been completed in recent years by NovaCopper and its previous parent company NovaGold Resources Inc. ("NovaGold"). The mineral resource for the Arctic Project is supported by 43 core holes (approximately 13,500 m) drilled by NovaGold and 92 core holes (approximately 17,600 m) drilled by previous owners Kennecott, and/or a Kennecott subsidiary. The geological and assay database have been reviewed and audited by Tetra Tech. Tetra Tech is of the opinion that the current drilling information is sufficiently reliable to interpret with confidence the boundaries for VMS mineralization and that the assay data are sufficiently reliable to support mineral resource estimation.
Leapfrog™ software (version 2.5.1) was used to review and verify the resource estimation domains, prior to being imported into Isatis™ software (version 2012.1) to prepare assay data for geostatistical analysis, variography, block model construction, metal grade estimation and mineral resource tabulation. Mineral Resources were estimated into five massive-sulphide and six semi-massive sulphide lenses, and then combined with waste for an overall grade for the 10x10x5m block. Extreme lead and gold assays were capped prior to compositing. Ordinary Kriging ("OK") and inverse distance to a power of two ("ID2") estimates were run, with OK used for resource reporting and ID2 used for validation. Search parameters were constrained within each mineralized domain and required an optimum number of 15 composites, minimum number of 5 composites, minimum number of 2 drill holes, and maximum search distance range of 200 metres. In general, blocks categorized as Indicated were supported by at least 2 drill holes within a 75 metre search radii, and blocks categorized as Inferred were supported by at least 2 drill holes within a 150 metre search radii.