Centerra Gold Announces 2024 Year-End Mineral Reserves and Resources, Including an Initial Resource at Goldfield; Provides Exploration Update
TSXV - TSX Venture Exchange · Lithium · Copper · Gold · Silver · Molybdenum · Nickel · Cobalt · Canada
All figures are in United States dollars unless otherwise stated. This news release contains forward-looking information that is subject to risk factors and assumptions as set out in the “Cautionary Note Regarding Forward-Looking Information” below.
TORONTO, Feb. 20, 2025 (GLOBE NEWSWIRE) -- Centerra Gold Inc. (“Centerra” or the “Company”) (TSX: CG) (NYSE: CGAU) announces its 2024 year-end estimates for mineral reserves and mineral resources. Proven and probable gold mineral reserves were 3.5 million ounces and proven and probable copper mineral reserves were 1,150 million pounds, as of December 31, 2024. Measured and indicated gold mineral resources were 6.8 million ounces as of December 31, 2024, which includes the initial gold mineral resource at the Goldfield Project (“Goldfield”) of 706 thousand ounces.
Centerra Year-End Gold Mineral Reserves and Mineral Resources ( 1)
| | 2024 | 2023 | | | | | | Property | Tonnes (kt) | Grade (g/t) | Contained Gold (koz) | Tonnes (kt) | Grade (g/t) | Contained Gold (koz) | | Total Proven and Probable Gold Mineral Reserves | | | | | | | | Mount Milligan Mine | 264,512 | 0.33 | 2,826 | 250,025 | 0.35 | 2,822 | | Öksüt Mine | 20,080 | 1.03 | 662 | 25,255 | 1.01 | 819 | | Total | 284,591 | 0.38 | 3,488 | 275,280 | 0.41 | 3,641 | | Total Measured and Indicated Gold Mineral Resources | | | | | | | | Mount Milligan Mine | 183,971 | 0.26 | 1,566 | 259,860 | 0.27 | 2,333 | | Öksüt Mine | 2,617 | 0.69 | 58 | 6,752 | 0.55 | 119 | | Kemess Open Pit | 111,682 | 0.27 | 980 | 111,682 | 0.27 | 980 | | Kemess Underground | 139,920 | 0.50 | 2,265 | 139,920 | 0.50 | 2,265 | | Kemess East | 93,454 | 0.39 | 1,182 | 93,454 | 0.39 | 1,182 | | Goldfield | 30,833 | 0.71 | 706 | - | - | - | | Total | 562,476 | 0.37 | 6,759 | 611,668 | 0.35 | 6,880 | | Inferred Gold Mineral Resources | | | | | | | | Mount Milligan Mine | 27,924 | 0.44 | 395 | 7,795 | 0.34 | 84 | | Öksüt Mine | 130 | 1.06 | 4 | 348 | 0.78 | 9 | | Kemess Open Pit | 13,691 | 0.26 | 116 | 13,691 | 0.26 | 116 | | Goldfield | 2,267 | 0.41 | 30 | - | - | - | | Total | 44,012 | 0.39 | 547 | 21,833 | 0.30 | 209 |
(1) As of December 31, 2024. Refer to Tables “Centerra Gold Inc. 2024 Year-End Mineral Reserve and Resource Summary – Gold” and “Centerra Gold Inc. 2024 Year-End Mineral Reserve and Resource Summary – Other Metals”, including their respective footnotes and the “Additional Footnotes” section below.
Mount Milligan Mine (“Mount Milligan”): In 2024, the Company replaced mined mineral reserves at Mount Milligan by upgrading mineral resources. Centerra has successfully extended the life of mine at Mount Milligan to 2036 by increasing the use of mined-out areas of the open pit for potential acid generating (“PAG”) waste storage. This has increased available storage capacity in the existing tailings facility and extended the overall mine life for the current mineral reserve estimate. Kemess Project (“Kemess”): The Kemess property has substantial gold and copper resources in a highly prospective district with significant infrastructure already in place, including: a 300 kilometre, 230 kilovolt power line, one of the longest privately owned power lines in British Columbia; a 50,000 tonnes per day nameplate processing plant, which would require some refurbishment and equipment replacements; site infrastructure including a camp, administration facilities, truck shop and warehouse; and tailings storage through in-pit and an existing facility, which is capable of expansion. Centerra is currently working to incorporate the results of a drilling campaign conducted in 2024 at Kemess into an updated open pit resource model. The program included over 11,400 metres of core drilling for exploration, geotechnical, and metallurgical testing purposes.
During 2024, Centerra commenced evaluation of technical concepts and engineering trade-off studies for potential restart options at Kemess. Early operating concepts include a combined open pit and conventional underground operation, which are expected to be less capital intensive and have a better cash flow profile than the previously permitted underground block cave concept. In addition to an exploration campaign in 2025 to further delineate the resources, the Company is planning on continuing to advance the technical studies that will include metallurgical testing for flowsheet optimization, mine plan optimization, materials handling infrastructure engineering, tailings design optimization, as well as initiation of environmental baseline studies. Early indications show potential for a long-life operation that takes advantage of the significant infrastructure already in place. The Company expects to provide an updated resource estimate and an accompanying update on the technical concept for Kemess in the second quarter of 2025.
Goldfield: The initial measured and indicated gold mineral resource at Goldfield was 706 thousand ounces of gold, as of December 31, 2024, which includes both oxide and transition material, principally in the Gemfield, McMahon, and Jupiter deposits. In conjunction with exploration drilling, the Company completed metallurgical testwork resulting in run-of-mine recoveries in the mid-60% range (see “Additional Footnotes” section at the end of this release for details on recoveries), which is in line with expectations for a heap leach project and is expected to lower the capital investment required for the project. Based on the size of the resource estimate, the project does not meet Centerra’s requirements to support near-term development. The Company remains committed to maximizing the project’s potential, while exploring strategic and commercial options for Goldfield.
Centerra Year-End Copper Mineral Reserves and Mineral Resources ( 1)
| | 2024 | 2023 | | | | | | Property | Tonnes (kt) | Grade (% Copper) | Contained Copper (Mlbs) | Tonnes (kt) | Grade (% Copper) | Contained Copper (Mlbs) | | Proven and Probable Copper Mineral Reserves | | | | | | | | Mount Milligan Mine | 264,512 | 0.20 | 1,150 | 250,025 | 0.17 | 961 | | Total | 264,512 | 0.20 | 1,150 | 250,025 | 0.17 | 961 | | Measured and Indicated Copper Mineral Resources | | | | | | | | Mount Milligan Mine | 183,971 | 0.18 | 732 | 259,860 | 0.15 | 851 | | Kemess Open Pit | 111,682 | 0.14 | 337 | 111,682 | 0.14 | 337 | | Kemess Underground | 139,920 | 0.25 | 779 | 139,920 | 0.25 | 779 | | Kemess East | 93,454 | 0.30 | 628 | 93,454 | 0.30 | 628 | | Total | 529,027 | 0.21 | 2,476 | 604,916 | 0.19 | 2,595 | | Inferred Copper Mineral Resources | | | | | | | | Mount Milligan Mine | 27,924 | 0.12 | 74 | 7,795 | 0.14 | 24 | | Kemess Open Pit | 13,691 | 0.16 | 48 | 13,691 | 0.16 | 48 | | Total | 41,615 | 0.13 | 121 | 21,486 | 0.15 | 72 |
(1) As of December 31, 2024. Refer to Tables “Centerra Gold Inc. 2024 Year-End Mineral Reserve and Resource Summary – Gold” and “Centerra Gold Inc. 2024 Year-End Mineral Reserve and Resource Summary – Other Metals”, including their respective footnotes and the “Additional Footnotes” section below.
Exploration Update
Exploration activities in the fourth quarter of 2024 included drilling, surface rock and soil sampling, geological mapping, and geophysical surveying, targeting gold and copy mineralization at the Company’s projects and properties in Canada, Türkiye, and the United States.
2024 Exploration Highlights
Confirming Mount Milligan’s long-life potential, the pit expanded to the west and southwest, due to significant intersections in the Goldmark and Saddle areas. Model expansion includes the south boundary area. Remodeling considers all holes drilled west of the Mount Milligan pit and resulted in defining the South Boundary inferred resource. At Kemess drilling was carried out in 2024 to assess the viability of start-up scenarios and open pit resource expansion. The goal was to expand near-surface mineralization west and southwest of the Kemess underground project. Resource delineation drilling for near surface oxide mineralization continued at the Goldfield project. Drilling intersected low-grade mineralization with a series of 10 to 30 metres at 0.4 grams per tonne (“g/t”). Most of the drilling was completed before the fourth quarter 2024, except at the Oakley project, in Idaho, United States (5,818 metres), Nallihan in Türkiye (4,829 metres) and Öksüt in Türkiye (421 metres). The drilling at Öksüt started late December 2024. Full year 2024 drilling totalled 72.3 kilometres, including greenfield projects.
2025 Exploration Outlook
Exploration expenditures in 2025 are expected to be $35 to $45 million, including $20 to $25 million of brownfield exploration primarily at Mount Milligan and Kemess, and $15 to $20 million of greenfield and generative exploration programs. Centerra is expected to continue to explore the western extension of the Mount Milligan deposit and perform infill drilling to upgrade the inferred resources to indicated. Approximately 25% of the 2025 exploration expenditures are allocated to drilling programs at Mount Milligan to upgrade the inferred resources between Goldmark and North Slope and to test the extension of the South Boundary mineralization. A total of 45 kilometres of drilling is planned for 2025 at Mount Milligan. Centerra is expected to continue to explore Kemess, where the 2024 drilling resulted in delineation of mineralization between the Kemess Main open pit and Nugget (Centra Ridge zone). The 2025 exploration program at Kemess is focused on upgrading the resources along the five-kilometre-long mineralized trend. Approximately 13% of the 2025 exploration expenditures are allocated to Kemess to drill 12.5 kilometres. In the United States, Centerra is expected to continue to explore for near surface oxide mineralization within the Goldfield district and at Oakley. Centerra is also expected to continue advancing exploration work at its greenfield projects, Green Springs in Nevada and Jones Creek in Utah. In Türkiye, Centerra is expected to commence phase 2 drilling at the Nallihan joint venture project and to continue to explore for near surface mineralization southeast of the Öksüt pit.
Mount Milligan
In 2024, the Company replaced mined mineral reserves at Mount Milligan by upgrading mineral resources. Ongoing exploration drilling program at the site is aimed at expanding the mineral resource base significantly to the west and southwest. In 2024, a total of 7,176 metres of infill drilling was completed in 25 drillholes, and 12,403 metres of brownfield exploration drilling was completed in 28 drillholes. Brownfield exploration focused on targets west of the current ultimate pit margins including the North Slope, Saddle West, and Boundary zones. The 2024 exploration drill results at the North Slope zone show potential for shallow as well as deep porphyry mineralization west of the ultimate pit boundary, adjacent to the Goldmark zone. Results from infill drilling in the MBX zone shows potential for resource expansion on the western pit wall margins and below the current pit boundary. The inclusion of all drillholes west of the Mount Milligan pit in the updated resource model resulted in the delineation of a potential satellite pit at south boundary. This area is one of the focus areas in the 2025 drilling campaign. Centerra continues to be encouraged by the significant mineral endowment and the potential for future resource additions at Mount Milligan. The Company is expected to invest approximately $9 to $12 million in exploration at Mount Milligan in 2025.
Mount Milligan Brownfield Drilling and Exploration
Figure 1: Plan view of Mount Milligan deposit showing 2024 resource shell.
Figure 2: Plan view of Mount Milligan deposit showing major porphyry trends.
Figure 3: East-West cross section of the Mount Milligan 2024 resource pit (looking north), showing gold and copper grade contours. The circled area is the 2025 target for infill drilling.
Figure 4: Long section view of Mount Milligan (looking northwest), showing gold and copper grade contours. Circled areas represent target areas for the 2025 infill drill program.
Figure 5: Plan view of Mt. Milligan showing the 2025 planned drilling program. Bright red holes are phase 1 priority holes intended to be completed by the end of the first quarter 2025. Drilling started in January 2025.
The DWBX zone is the depth extension of the WBX porphyry-style gold-copper mineralisation currently mined in the pit. Mineralization is associated with potassic alteration and early quartz veins within the DWBX stock and stock margins. Near surface and south of the DWBX is the King Richard zone. Results received to-date show the potential to extend the open pit to mine DWBX, King Richard, and DWBX Extension. Some selected significant results received during the year include:
Hole #24-1531: 26.0m @ 0.71 g/t Au, 0.188% Cu from 58m
Hole #24-1569: 37.8m @ 0.48 g/t Au, 0.229% Cu from 115m
Hole #24-1572: 30.3m @ 0.55 g/t Au, 0.176% Cu from 83m
Hole #24-1556: 48.4m @ 0.32 g/t Au, 0.204% Cu from 139m
Hole #24-1571: 58.0m @ 0.24 g/t Au, 0.068% Cu from 68m
Hole #24-1556: 83.8m @ 0.15 g/t Au, 0.127% Cu from 214m
Hole #24-1554: 73.0m @ 0.16 g/t Au, 0.168% Cu from 248m
Hole #24-1564: 18.7m @ 0.60 g/t Au, 0.161% Cu from 21m
The Goldmark zone is directly west of the current Mount Milligan pit design, situated above the high grade DWBX zone. In 2024, drilling continued to test the western extent of the Goldmark mineralisation that had been intersected in previous drill programs. Shallow porphyry-style gold and copper mineralisation is hosted at the margins of dykes and the Goldmark stock. High gold-low copper (“HGLC”) style mineralisation occurs throughout the zone. The results show potential for shallow resource additions and the extension of mineralisation west of the existing pit boundary. Significant results include:
Hole #24-1529: 65.0m @ 0.22 g/t Au, 0.191% Cu from 497m
Hole #24-1529: 19.2m @ 0.41 g/t Au, 0.038% Cu from 370m
Hole #24-1532: 20.0m @ 0.28 g/t Au, 0.030% Cu from 34m
Hole #24-1532: 11.5m @ 0.32 g/t Au, 0.205% Cu from 275m
The North Slope zone is approximately 1.5 kilometres west of the western margins of the existing pit boundary. Assays show multiple localized shallow zones of mineralisation related to the North Slope stock, with higher-grade porphyry-style gold and copper mineralization intersected near surface and at depth. Significant results include:
Hole #24-1533: 42.3m @ 0.41 g/t Au, 0.241% Cu from 25m
Hole #24-1533: 3.0m @ 4.47 g/t Au, 0.078% Cu from 448m
Hole #24-1536: 41.8m @ 0.33 g/t Au, 0.144% Cu from 244m
Hole #24-1536: 68.6m @ 0.16 g/t Au, 0.172% Cu from 305m
Hole #24-1536: 64.9m @ 0.29 g/t Au, 0.173% Cu from 378m
Hole #24-1543: 85.8m @ 0.24 g/t Au, 0.173% Cu from 336m
Hole #24-1543: 101.3m @ 0.20 g/t Au, 0.179% Cu from 451m
Hole #24-1563: 7.1m @ 2.21 g/t Au, 0.142% Cu from 81m
Hole #24-1563: 13.5m @ 1.09 g/t Au, 0.086% Cu from 32m
Hole #24-1566: 4.9m @ 8.11 g/t Au, 0.024% Cu from 238m
Hole #24-1566: 40.0m @ 0.33 g/t Au, 0.012% Cu from 136m
Hole #24-1567: 23.5m @ 4.27 g/t Au, 0.183% Cu from 160m
Hole #24-1567: 5.0m @ 5.01 g/t Au, 0.147% Cu from 291m
Hole #24-1567: 27.0m @ 2.83 g/t Au, 0.143% Cu from 342m
Hole #24-1567: 27.7m @ 3.63 g/t Au, 0.129% Cu from 483m
Kemess Project
In 2024, 11,430 metres of core drilling was completed in 31 drillholes. These drillholes are expected to be incorporated into an updated mineral resource in the second quarter of 2025. The 2024 drill program targeted the area between the known mineralization at Nugget and the upper portion of the Kemess Underground zones. Significant drill intersections were received, confirming that the mineralization continues approximately five kilometres along strike. Geologic modeling and a preliminary resource estimate show continuous mineralization between the Nugget and Kemess North zone areas, which is expected to be the focus for the 2025 drill program. The program aims to upgrade inferred resources to indicated reserves and also to test, and potentially, confirm high grade mineralization in the deep Kemess offset zone. Centerra is encouraged by the large mineralization at Kemess and believes that it can be a future source of gold and copper production with a long mine life.
Some of the significant 2024 results include:
Hole #KN-24-013: 435m @ 0.43g/t Au, 0.23% Cu from 172m
Hole #KN-24-013: 402m @ 0.42g/t Au, 0.20% Cu from 47m
Hole #KN-24-017: 382m @ 0.38g/t Au, 0.19% Cu from 8m
Hole #KN-24-014: 342m @ 0.35g/t Au, 0.07% Cu from 56m
Hole #KN-24-019: 341m @ 0.34g/t Au, 0.16% Cu from 4m
Hole #KN-24-021: 311m @ 0.37g/t Au, 0.18% Cu from 0m
Figure 6: A long sectional view of the Kemes deposit showing a 0.2 g/t Au shell. The areas previously studied for a potential block cave mining scenario are shown within the dotted areas. The 2023 conceptual optimized pit is shown in grey.
Goldfield Project (“Goldfield”)
In 2024, Centerra continued to explore within the Goldfield district, focusing on exploring near surface oxide mineralization. The 2024 drill program consisted of 175 drillholes over 20,028 metres with 45 core holes totaling 5,386 metres and 130 reverse circulation drillholes totaling 14,642 metres. Drilling at Goldfield’s other target areas did not yield meaningful results.
The Jupiter prospect exploration program focused on oxidized mineralization with an up-dip projection trending shallower on the eastern portion of the prospect. The Jupiter prospect is the northerly extension of the Gemfield deposit. Drilling was facilitated by land agreements and drill permits completed in late 2023. Results proved the up-dip projection of oxide mineralization in the prospect, however, the grades and thickness are uneconomic to include an appreciable amount of material into an optimized pit shell when the prevailing economic parameters were applied. A series of small satellite pits were delineated to be included in the Goldfield initial resource. Some of the significant results received for Jupiter include:
Hole #GEM24R279: 19.8m @ 2.55 g/t Au, 16.38 g/t Ag from 87m
Hole #GEM24R256: 36.6m @ 1.04 g/t Au, 1.09 g/t Ag from 20m
Hole #GEM24R319: 6.1m @ 5.36 g/t Au, 5.50 g/t Ag from 0m
Hole #GEM24R286: 24.4m @ 1.09 g/t Au, 1.96 g/t Ag from 23m
Hole #GEM24R249: 35.1m @ 0.41 g/t Au, 0.66 g/t Ag from 40m
Hole #GEM24R291: 30.5m @ 0.46 g/t Au, 0.70 g/t Ag from 15m
Hole #GEM24R289: 30.5m @ 0.40 g/t Au, 0.91 g/t Ag from 15m
Hole #GEM24R239: 32.0m @ 0.38 g/t Au, 1.04 g/t Ag from 11m
Oakley Project (“Oakley”)
The 2024 drill program at Oakley completed 32 drillholes over 5,818 metres with 18 core holes totaling 2,995 metres and 14 reverse circulation drillholes totaling 2,823 metres. In 2024, drilling at the Cold Hill and Blue Hill prospects focused on expanding the known gold mineralization, while drilling at Red Rock and White Rock focused on new, untested drill targets.
At the Cold Hill target, four holes encountered significant mineralization, primarily represented by silicified pebble to cobble conglomerate and silicified volcanic ash, and with minor intersections within the underlying Paleozoic limestone, represented by decalcification and silicification. These intersections continue to define the lateral extent and width of the mineralization at Cold Hill. Some of the significant results received for Cold Hill include:
Hole #CC-24-04: 20.3m @ 0.24 g/t Au, 1.47 g/t Ag from 8m
Hole #CC-24-04: 20.9m @ 0.50 g/t Au, 4.00 g/t Ag from 37m
Hole #CC-24-07: 9.9m @ 0.69 g/t Au, 1.19 g/t Ag from 192m
Hole #CC-24-07: 1.0m @ 4.54 g/t Au, 0.90 g/t Ag from 200m
Drilling at the Blue Hill prospect focused on testing the margins of the known mineralization and following up on the higher-grade intersections identified in historic drilling. Mineralization was encountered in the most southwestern drillholes in the prospect, which shows the potential for additional mineralization towards the southwest. The mineralization is associated with strong silicification of the pebble to cobble conglomerate and silicification of the volcanic ash beds. Significant intersections are listed below.
Hole #BHC24R001: 19.8m @ 0.42 g/t Au, 4.19 g/t Ag from 24m
Earlier from Midland Exploration Inc.
- Centerra Gold Reports Fourth Quarter and Full Year 2024 Results and 2025 Outlook; Strong Cash Flow from Operating Activities and $625 Million in Cash and Cash Equivalents
- Centerra Gold Provides Notice of Fourth Quarter 2024 Results Release and Conference Call
- Centerra Gold Announces TSX Acceptance of Renewed Normal Course Issuer Bid