OreStocks

Lundin Mining Corporation press release

Lundin Mining Second Quarter 2024 Results

TSX - Toronto Stock Exchange · Copper · Gold · Silver · Iron · Molybdenum · Nickel · Canada · Corporate Finance

Canada NewsWire

[](https://mma.prnewswire.com/media/2472235/Lundin_Mining_Corporation_Lundin_Mining_Second_Quarter_2024_Resu.html)

VANCOUVER, BC , July 30, 2024 /CNW/ - (TSX: LUN) (Nasdaq Stockholm: LUMI) Lundin Mining Corporation ("Lundin Mining" or the "Company") today reported its second quarter 2024 financial results. Unless otherwise stated, results are presented in United States dollars on a 100% basis.

Jack Lundin , President and CEO commented, "During the quarter we generated record quarterly revenue of $1.1 billion which contributed to a strong financial performance for the Company. Adjusted EBITDA 1 for the quarter was $461 million and free cash flow from operations 1 was $338 million driven by stronger commodity prices and working capital inflows.

"At Candelaria, while mill throughput in the first half of the year was strong, we expect to achieve a significant step-up in production in the second half of the year with planned higher grades and higher mining rates from ore in Phase 11. This production step-up has started to materialize during the month of July from the open pit.

"Our team remains dedicated to enhancing operational performance, prioritizing safety and cost optimization. Cash costs 1 for the quarter were at the lower end of our guidance range. We are well-positioned for a strong second half of the year and are on track to meet our consolidated production guidance for copper, gold, and zinc. Additionally, we have reduced our guidance for sustaining capital expenditures by $45 million ."

Second Quarter Operational and Financial Highlights

Copper Production: Consolidated production of 79,708 tonnes of copper in the second quarter. Other Production: During the quarter, a total of 47,460 tonnes of zinc, 1,721 tonnes of nickel and approximately 32,000 ounces of gold were produced. Revenue: $1,083.6 million in the second quarter with a realized copper price 1 of $4.79 /lb. Net Earnings and Adjusted Earnings 1 : Net earnings attributable to shareholders of the Company were $121.6 million or $0.16 per share in the second quarter with adjusted earnings of $122.1 million or $0.16 per share. Adjusted EBITDA 1 : $460.9 million generated during the quarter. Cash Generation: Cash provided by operating activities was $491.8 million and free cash flow from operations 1 was $337.5 million , which was increased by a working capital release of $121.9 million . Growth: On July 2, 2024 , the Company exercised its option to increase ownership in Caserones to 70%, which adds an additional 25,000 tonnes of attributable copper production to Lundin Mining's production profile 2 . Sustainability Report: On July 10, 2024 the Company published its annual 2023 Sustainability Report that highlights the Company's material environmental, health & safety, governance and social performance during the year. Outlook: Second quarter 2024 production and cash costs were aligned with expectations, the Company's full year guidance remains unchanged with the exception of nickel: Caserones: Annual copper production guidance range for the Caserones mine for 2024 has been increased to 124,000 - 135,000 tonnes (previously 120,000 - 130,000 tonnes). Cash cost guidance for Caserones remains unchanged. Eagle Mine: Annual nickel production guidance range for the Eagle mine for 2024 has been reduced to 7,000 - 9,000 tonnes (previously 10,000 - 13,000 tonnes) and the copper production guidance range has been reduced to 5,000 - 7,000 tonnes (previously 9,000 - 12,000 tonnes). Cash cost guidance per pound of nickel for the Eagle mine has increased to $3.20 /lb - $3.40 /lb (previously $2.80 /lb - $3.00 /lb) Sustaining Capital Expenditures: Will be reduced by $45 million and are expected to total $795 million (previously $840 million ) due to reductions in planned spending at Caserones, Neves-Corvo and Zinkgruvan.

| _ | | 1 These are non-GAAP measures. Please refer to the Company's discussion of non-GAAP and other performance measures in its Management's Discussion and Analysis ("MD&A") for the three and six months ended June 30, 2024 and the Reconciliation of Non-GAAP measures section at the end of this news release. | | 2 Based on Caserones 2024 production guidance as outlined in the news release 'Lundin Mining Provides 2024 Guidance & Announces 2023 Production Results' dated January 14, 2024. |

Summary Financial Results

| | Three months ended

June 30, | | Six months ended

June 30, | | | | | US$ Millions (except per share amounts) | 2024 | 2023 | | 2024 | 2023 | | | Revenue | 1,083.6 | 588.5 | | 2,020.6 | 1,339.9 | | | Gross profit | 279.5 | 52.8 | | 464.9 | 266.2 | | | Attributable net earnings a | 121.6 | 59.1 | | 135.5 | 205.7 | | | Net earnings | 156.7 | 61.3 | | 215.3 | 226.6 | | | Adjusted earnings a,b | 122.1 | 45.6 | | 167.3 | 171.3 | | | Adjusted EBITDA b | 460.9 | 191.8 | | 823.7 | 528.7 | | | Basic earnings per share ("EPS") a | 0.16 | 0.08 | | 0.18 | 0.27 | | | Diluted EPS a | 0.16 | 0.08 | | 0.17 | 0.27 | | | Adjusted EPS a,b | 0.16 | 0.06 | | 0.22 | 0.22 | | | Cash provided by operating activities | 491.8 | 194.8 | | 759.3 | 406.7 | | | Adjusted operating cash flow b | 369.9 | 110.6 | | 683.5 | 345.7 | | | Adjusted operating cash flow per share b | 0.48 | 0.14 | | 0.88 | 0.45 | | | Free cash flow from operations b | 337.5 | 20.7 | | 405.2 | 91.8 | | | Free cash flow b | 236.8 | (84.6) | | 235.1 | (118.8) | | | Cash and cash equivalents | 452.8 | 190.2 | | 452.8 | 190.2 | | | Net debt excluding lease liabilities b | 893.8 | 201.3 | | 893.8 | 201.3 | | | Net debt b | 1,152.9 | 229.8 | | 1,152.9 | 229.8 | |

| a Attributable to shareholders of Lundin Mining Corporation. | | | | b These are non-GAAP measures. Please refer to the Company's discussion of non-GAAP and other performance measures in its Management's Discussion and Analysis for the three and six months ended June 30, 2024 and the Reconciliation of Non-GAAP Measures section at the end of this news release. | | |

For the three months ended June 30, 2024 , the Company generated revenue of $1,083.6 million , driven by 78,662 tonnes of copper sold at a realized price of $4.79 /lb. Revenue benefited from higher realized copper and zinc prices, including $94.5 million positive provisional pricing adjustments on prior period concentrate sales. Gross profit of $279.5 million and Adjusted EBITDA of $460.9 million in the three months ended June 30, 2024 reflect higher realized copper and zinc prices despite the impacts of planned lower grades and maintenance activities on copper concentrate sales from Candelaria and Caserones, respectively. Net earnings attributable to shareholders of the Company were $121.6 million or $0.16 per share in the three months ended June 30, 2024 , and included higher tax expense due to higher taxable earnings and the utilization of prior period tax losses. Adjusted earnings attributable to shareholders of the Company for the three months ended June 30, 2024 were $122.1 million or $0.16 per share after removing a loss on foreign exchange due to the translation of deferred tax balances and expenses relating to the partial suspension of underground operations at Eagle, among other things. Cash and cash equivalents as at June 30, 2024 were $452.8 million . Cash provided by operating activities amounted to $491.8 million and cash used to fund investing activities amounted to $252.2 million . The Company had a net debt excluding lease liabilities 1 balance of $893.8 million as at June 30, 2024 ( December 31, 2023 - $946.2 million ). Free cash flow 1 for the three months ended June 30, 2024 of $236.8 million reflected higher copper and zinc realized prices, positive working capital changes and reduced capital expenditure at Candelaria. During the three months ended June 30, 2024 , the Company entered into zero cost collar contracts in the total amount of $222 million (equivalent to BRL 1.1 billion ) with collar ranges of BRL 5.00 to BRL 6.11 . As at July 30, 2024 , the Company had a cash balance of approximately $288.0 million and a net debt excluding lease liabilities balance of approximately $1,338.0 million .

| | | 1 These are non-GAAP measures. Please refer to the Company's discussion of non-GAAP and other performance measures in its Management's Discussion and Analysis ("MD&A") for the three and six months ended June 30, 2024 and the Reconciliation of Non-GAAP measures section at the end of this news release. |

Operational Performance

Total Production

| (Contained metal) a | 2024 | 2023 | | | | | | | | YTD | Q2 | Q1 | Total | Q4 | Q3 | Q2 | Q1 | | | Copper (t) b | 167,721 | 79,708 | 88,013 | 314,798 | 103,337 | 89,942 | 60,057 | 61,462 | | Zinc (t) | 93,148 | 47,460 | 45,688 | 185,161 | 50,719 | 49,774 | 36,115 | 48,553 | | Nickel (t) | 4,976 | 1,721 | 3,255 | 16,429 | 3,729 | 4,290 | 4,686 | 3,724 | | Gold (koz) b | 65 | 32 | 33 | 149 | 44 | 35 | 34 | 36 | | Molybdenum (t) b | 1,578 | 714 | 864 | 2,024 | 928 | 1,096 | — | — | | a. Tonnes (t) and thousands of ounces (koz) | | | | | | | | | | b. Candelaria and Caserones production is on a 100% basis. | | | | | | | | |

_Candelaria (80% owned): _Candelaria produced 31,170 tonnes of copper and approximately 17,000 ounces of gold in concentrate on a 100% basis in the three months ended June 30, 2024 . Production in the quarter was impacted by lower grades and recoveries, partially offset by higher throughput. During the three months ended June 30, 2024 , mining rates were impacted by the interface of the open pit and historic underground mining stopes, requiring more stockpiled ore to be processed which reduced grades and recoveries. Access to higher grade ore is anticipated in the second half of 2024 as per the mine sequence. Three of four stopes have now been filled and blasted, with work on the fourth expected to begin in Q3, and not expected to impact production in the second half of 2024. Production costs were reduced by lower sales volumes and favourable foreign exchange as a result of the CLP weakening against the US dollar; however, cash cost of $2.18 /lb was negatively impacted by lower sales volumes.

_Caserones (51% owned): _Caserones produced 29,775 tonnes of total copper and 714 tonnes of molybdenum on a 100% basis in the three months ended June 30, 2024 . Copper and molybdenum concentrate production was impacted in the quarter by extended mill maintenance and weather events which reduced mining activities and limited tailings deposition. Recoveries were also temporarily reduced by changes in the mining sequence and flotation circuit disruptions. Production costs in the quarter were lower than planned primarily due to lower copper concentrate and molybdenum sales volume, as well as favourable foreign exchange. Cash cost also benefitted from favourable foreign exchange.

_Chapada (100% owned): _Chapada produced 9,106 tonnes of copper and approximately 15,000 ounces of gold in concentrate in the three months ended June 30, 2024 and was impacted by lower grades and recoveries combined with lower mill availability due to unplanned conveyor maintenance and vibration screen failure. Lower grades were a result of a shift to processing increased amounts of stockpiled ore and an optimized mine plan that significantly reduces waste movement. Production costs were reduced by lower sales volumes and favourable foreign exchange. Cash cost of $2.05/lb benefited from higher gold by-product credits combined with favourable foreign exchange and mining cost decreases due to operational improvements.

_Eagle (100% owned): _Eagle produced 1,721 tonnes of nickel and 1,563 tonnes of copper in the three months ended June 30, 2024 . A fall of ground in the lower ramp restricted access to Eagle East, limiting production. Mining rates are expected to be reduced until late 2024 while ramp rehabilitation is completed, deferring the extraction of ore from Eagle East into future years. Production costs were reduced by lower sales volumes and royalty expense, partially offset by higher maintenance costs. Nickel cash cost 1 of $3.23 /lb was impacted by lower sales volumes, partially offset by higher by-product credits.

_Neves-Corvo (100% owned): _Neves-Corvo produced 7,347 tonnes of copper and 25,696 tonnes of zinc in the three months ended June 30, 2024 , both of which were impacted by lower grades due to changes in mine sequencing as a result of Lombador south requiring additional development work. Production costs increased due to an increase in sales volumes and cash cost of $1.70/lb benefited from increased sales volumes and higher by-product credits.

_Zinkgruvan (100% owned): _Zinkgruvan produced 21,764 tonnes of zinc and 8,966 tonnes of lead in the three months ended June 30, 2024 reflecting higher throughput and grades. Copper production of 747 tonnes was impacted by reduced availability of copper ore. Production costs increased due to higher sales volumes and zinc cash cost of $0.39 /lb reflected lower copper by-product credits.

Outlook

Production and cash cost guidance for 2024 has been updated from that disclosed in the Company's Management's Discussion and Analysis for the year ended December 31, 2023 .

The Company remains on track to meet annual production and cash cost guidance for all metals with the exception of nickel, and has reduced sustaining capital expenditure guidance from $840 million to $795 million with reductions at Caserones, Neves-Corvo, and Zinkgruvan. Expenditure guidance related to the Josemaria Project of $225 million and exploration of $48 million each remain on target for 2024.

Metal production continues to be weighted to the second half of the year at Candelaria, Chapada and Neves-Corvo due to mine sequencing and resultant forecasted grade profiles. Grade is expected to increase significantly at Candelaria in the second half of 2024 once access is opened to higher-grade ore. As a result of production challenges at Neves-Corvo in the first half of 2024, copper production at that operation continues to track to the lower end of its annual production guidance range. In the first half of 2024, cash cost per pound at most operations benefited from increased realized prices on by-product sales.

Guidance at Caserones has been increased to reflect production from the first half of the year and expected throughput and grades for the remainder of the year. At the Eagle mine, a fall of ground in the lower ramp restricted access to Eagle East, limiting production. Mining rates are expected to be reduced until late 2024 while ramp rehabilitation is completed, deferring the extraction of ore from Eagle East into future years. As a result, the annual nickel and copper production guidance ranges for the Eagle mine for 2024 have been reduced.

2024 Production and Cash Cost Guidance

| | | | Guidance a | Revised Guidance | | | | | (contained metal) | Production | Cash Cost ($/lb) b | Production | Cash Cost ($/lb) b | | | | Copper (t) | Candelaria (100%) | 160,000 – 170,000 | 1.60 – 1.80 c | 160,000 – 170,000 | 1.60 – 1.80 c | | | | Caserones (100%) | 120,000 – 130,000 | 2.60 – 2.80 | 124,000 – 135,000 | 2.60 – 2.80 | | | | Chapada | 43,000 – 48,000 | 1.95 – 2.15 d | 43,000 – 48,000 | 1.95 – 2.15 d | | | | Eagle | 9,000 – 12,000 | | 5,000 – 7,000 | | | | | Neves-Corvo | 30,000 – 35,000 | 1.95 – 2.15 c | 30,000 – 35,000 | 1.95 – 2.15 c | | | | Zinkgruvan | 4,000 – 5,000 | | 4,000 – 5,000 | | | | | Total | 366,000 – 400,000 | | 366,000 – 400,000 | | | | Zinc (t) | Neves-Corvo | 120,000 – 130,000 | | 120,000 – 130,000 | | | | | Zinkgruvan | 75,000 – 85,000 | 0.45 – 0.50 c | 75,000 – 85,000 | 0.45 – 0.50 c | | | | Total | 195,000 – 215,000 | | 195,000 – 215,000 | | | | Nickel (t) | Eagle | 10,000 – 13,000 | 2.80 – 3.00 | 7,000 – 9,000 | 3.20 – 3.40 | | | Gold (koz) | Candelaria (100%) | 100 – 110 | | 100 – 110 | | | | | Chapada | 55 – 60 | | 55 – 60 | | | | | Total | 155 – 170 | | 155 – 170 | | | | Molybdenum (t) | Caserones (100%) | 2,500 - 3,000 | | 2,500 – 3,000 | |

| a. Guidance as outlined in the Company's Management Discussion and Analysis ("MD&A") for the year ended December 31, 2023.

b. Cash costs are based on various assumptions and estimates, including but not limited to: production volumes, commodity prices (Cu: $3.75/lb, Zn: $1.10/lb, Pb: $0.90/lb, Au: $1,800/oz, Mo: $20.00/lb, Ag: $23.00/oz), foreign exchange rates (€/USD:1.05, USD/SEK:10.50, USD/CLP:850, USD/BRL:5.00) and production costs. Cash cost is a non-GAAP measure - see the Company's Management Discussion and Analysis for the three and six months ended June 30, 2024 and the Reconciliation of Non-GAAP Measures at the end of this news release.

c. 68% of Candelaria's total gold and silver production are subject to a streaming agreement, and silver production at Zinkgruvan and Neves-Corvo are also subject to streaming agreements. Cash costs are calculated based on receipt of approximately $429/oz gold and $4.28/oz to $4.68/oz silver.

d. Chapada's cash cost is calculated on a by-product basis and does not include the effects of its copper stream agreements. Effects of the copper stream agreements are reflected in copper revenue and will impact realized price per pound. |

2024 Capital Expenditure Guidance b

| | ($ millions) | Guidance a | Revisions | Revised Guidance | | | Candelaria (100% basis) | 300 | — | 300 | | | Caserones (100% basis) | 205 | (30) | 175 | | | Chapada | 110 | — | 110 | | | Eagle | 25 | — | 25 | | | Neves-Corvo | 125 | (10) | 115 | | | Zinkgruvan | 75 | (5) | 70 | | | Other | — | — | — | | | Total Sustaining | 840 | (45) | 795 | | | Josemaria | 225 | — | 225 | | | Total Capital Expenditures | 1,065 | (45) | 1,020 |

| | a. Guidance as outlined in the Company's Management Discussion and Analysis ("MD&A") for the year ended December 31, 2023.

b. Sustaining capital expenditure is a supplementary financial measure and expansionary capital expenditure is a non-GAAP measure - see the Company's Management Discussion and Analysis for the three and six months ended June 30, 2024 and the Reconciliation of Non-GAAP Measures at the end of this news release. |

Exploration

During the quarter ended June 30, 2024 , exploration activity focused on in-mine and near-mine targets at the Company's operations. Exploration drilling at Zinkgruvan was focused on resource expansion and drilling at Candelaria was focused on Candelaria Norte and La Espanola. Drilling at Chapada concentrated on delineating the high-grade, near-mine trend at Corpo Sul, adding high grade resources to Sauva and testing geochemical anomalies in the Sauva area Curicaca and Curio.

At Caserones, exploration activity remains lower during the winter season. Exploration drilling continues in the lower portion of the mineral resource in search of higher-grade copper breccia bodies that could improve the average grade of the resource, and potentially expand it. Near-mine drilling at Angelica has been paused for winter since April.

At Josemaria, seasonal exploration drilling ended in early April at the Cumbre Verde Target, located west of the Josemaria ore body. Six holes were drilled targeting the same mineralized system and structures that hosted high grade mineralization on the neighbouring property that may potentially run towards the Cumbre Verde Target. Initial results highlight favorable levels of copper/gold/silver mineralization in veins and porphyry. The data obtained will help further refine and target this mineralization. Work will continue throughout the remainder of 2024 with drilling to recommence after the winter season.

There was no exploration drilling at Neves-Corvo and Eagle in the quarter.

About Lundin Mining

Lundin Mining is a diversified Canadian base metals mining company with projects and operations in Argentina , Brazil , Chile , Portugal , Sweden and the United States of America , primarily producing copper, zinc, nickel and gold.

The information in this release is subject to the disclosure requirements of Lundin Mining under the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set out below on July 30, 2024 at 14:30 Vancouver Time.