Largo Resources Announces Second Quarter 2020 Results Highlighted by Continued Low-cost Operations; Overall Sales and Trading Performance In-Line with Expectations

TSX - Toronto Stock Exchange · Vanadium · Titanium · Iron · Platinum · Palladium · Gold · Tungsten · Molybdenum · Canada

Canada NewsWire

TORONTO, Aug. 13, 2020

All dollar amounts are in U.S. dollars, unless otherwise noted.

Q2 2020 Highlights

Production of 2,562 tonnes (5.6 million pounds1) of V2O5, an increase of 2.0% over Q2 2019 Two consecutive months of V2O5production above nameplate capacity: 1,052 tonnes in May 2020and 1,030 tonnes in June 2020 Global V2O5recovery rate2of 80.8%; Second quarter of strong global recoveries in 2020 Solid financial position: Cash at June 30, 2020totaled $78.2 million Record low cash operating costs excluding royalties3of $1.89per lb of V2O5 ,44% decrease over Q2 2019 (after tax credit benefits of $2.2 million) Revenues of $8.4 million(net of the re-measurement of trade receivables / payables of $2.4 millionon vanadium sales from contracts with customers of $10.8 million) Net loss of $7.0 millionand a loss per share of $0.01 Company maintains its 2020 sales, cost and production guidance

Other Significant Highlights

2019 Sustainability Report released: Including improved performance metrics and new reporting standards Nameplate capacity increase by 10%: Planned kiln upgrades and cooler maintenance scheduled for Q4 2020 with a capex of $1.3 million 2020 drilling program underway following delays caused by COVID-19

TORONTO, Aug. 13, 2020/CNW/ - Largo Resources Ltd. ("Largo" or the "Company") (TSX: LGO) (OTCQX: LGORF) today announces its second quarter 2020 financial and operating results with revenues of $8.4 millionfrom vanadium pentoxide ("V2O5") equivalent sales of 1,018 tonnes. Production from the Maracás Menchen Mine in Q2 2020 was 2,562 tonnes (5.6 million lbs1) of V2O5produced at an average global recovery rate4of 80.8%.

Paulo Misk, President and Chief Executive Officer for Largo, stated_: "The Company's balance sheet and financial position remains solid exiting Q2 2020. Operations performed well during the quarter following our preventative maintenance program and the Company's cash balance at the end of Q2 2020 was $78.2 million. Although profitability was impacted by lower recognized sales during the quarter, the Company's working capital investment was necessary to fill our sales pipeline and build strategic global V2O5 stockpiles in order to fulfil customer demand going forward. Also, despite some minor delays caused by the COVID-19 pandemic, our sales and trading performance remains in-line with expectations. We continue to maintain the Company's 2020 sales guidance of 9,500 to 10,000 tonnes of V2O5 as we realize the economic benefits associated with our commercial independence. Largo has demonstrated substantially lower unit costs versus Q2 2019, despite the fact that such costs now include sales and distribution costs (while under the previous off-take agreement, the Company's sales and marketing commissions were netted off against revenue)."_

He continued:_"On the market front, Chinese V2O5prices strengthened by approximately 15% to $6.95per lb during Q2 2020 as a result of increased steel sector demand. We continue to receive inquires for our products from end users and remain very optimistic about expected future demand growth as a result of recently announced stimulus programs, globally. Additionally, despite experiencing a period of low demand within the aerospace industry, we continue to prioritize increasing our high purity vanadium customer portfolio, particularly following the completion of our vanadium trioxide plant next year. Our focus remains on capturing these high value sales when demand returns to normalized levels as well as additional sales opportunities in new jurisdictions as the preferred producer and supplier of high purity vanadium."_

He concluded: "I am also very encouraged by the support and dedication shown by our entire team during these challenging times while at the same time achieving operational targets. Since March 2020, our team has supported local seamstress businesses who have produced over 230,000 protective masks which have aided in the fight against the spread of COVID-19 in Maracás. Going forward, we continue to prioritize the health and safety of our workforce and extend our support to our local communities as we proactively manage the circumstances related to the global COVID-19 pandemic."

A summary of the operational and financial performance for Q2 2020 is provided in the tables below. Effective May 1, 2020, the Company's Canadian and Irish entities have changed their functional currency to the U.S. dollar and the Company has changed its presentation currency from Canadian dollar to the U.S. dollar. Prior period comparative information is restated in U.S. dollars to reflect the change in presentation currency.

Financial

| | | | | | | | | | | | | Three months ended | | Six months ended | | | | | | | | June 30,

2020 | | June 30, 2019 | | June 30, 2020 | | June 30, 2019 | | Revenues | $ | 8,350 | $ | 21,963 | $ | 50,259 | $ | 55,168 | | Operating costs | | (9,561) | | (24,815) | | (35,809) | | (46,598) | | Direct mine and mill costs | | (2,180) | | (16,800) | | (19,674) | | (31,367) | | Net income (loss) before tax | | (5,533) | | (15,132) | | (1,652) | | (14,116) | | Income tax (expense) recovery | | - | | 102 | | - | | (732) | | Deferred income expense | | (1,479) | | (268) | | (1,017) | | (1,869) | | Net income (loss) | | (7,012) | | (15,298) | | (2,669) | | (16,717) | | Basic earnings (loss) per share | | (0.01) | | (0.03) | | (0.00) | | (0.03) | | Diluted earnings (loss) per share | | (0.01) | | (0.03) | | (0.00) | | (0.03) | | | | | | | | | | | | Cash provided (used) before non-cash working capital items | $ | 1,028 | $ | 406 | $ | (294) | $ | 11,697 | | Net cash (used in) provided by operating activities | | (63,649) | | 22,341 | | (64,631) | | 88,871 | | Net cash provided by (used in) financing activities | | 777 | | (5,116) | | 27,517 | | (73,050) | | Net cash (used in) investing activities | | (5,221) | | (14,195) | | (8,601) | | (20,355) | | Net change in cash | | (67,079) | | 1,868 | | (49,284) | | (5,865) | | | | | | | | | | | | | | | | | | | | As at | | | | | | | | June 30,

2020 | | December 31, 2019 | | Cash | | | | | $ | 78,215 | | 127,499 | | Working capital5 | | | | | | 80,756 | | 78,380 |

Operational

| | | | | | Maracás Menchen Mine Production | | Q2 2020 | Q2 2019 | | | | | | | Total Ore Mined (tonnes) | | 257,357 | 308,858 | | Ore Grade Mined - Effective Grade6(%) | | 1.20 | 1.21 | | | | | | | Effective Grade of Ore Milled6(%) | | 1.29 | 1.49 | | Concentrate Produced (tonnes) | | 99,059 | 102,320 | | Grade of Concentrate (%) | | 3.20 | 3.30 | | Contained V2O5(tonnes) | | 3,174 | 3,380 | | | | | | | Crushing Recovery (%) | | 97.7 | 98.0 | | Milling Recovery (%) | | 94.7 | 97.9 | | Kiln Recovery (%) | | 91.7 | 88.8 | | Leaching Recovery (%) | | 99.1 | 95.7 | | Chemical Plant Recovery (%) | | 96.1 | 97.1 | | Global Recovery (%)2 | | 80.8 | 79.1 | | | | | | | V2O5produced (Flake + Powder) (tonnes) | | 2,562 | 2,515 | | V2O5produced (equivalent pounds)1 | | 5,648,236 | 5,544,619 | | Cash operating costs3per pound | $ | $2.57 | $3.59 | | Cash operating costs excluding royalties3per pound | $ | $1.89 | $3.34 | | Total cash costs3 | $ | $3.68 | | | Revenues per pound sold7 | $ | $3.72 | $4.02 |

Second Quarter 2020 Financial Results

During Q2 2020, the Company recognized revenues of $8.4 million($22.0 millionin Q2 2019) from sales of 1,018 tonnes of V2O5equivalent. The low volume of sales in May and June was expected and is attributable to the Company's sales now typically being recognized at the time of delivery, which can take a few months from the time of shipment from Brazil. The Company's total sales of VPURE+™ products in the six months ended June 30, 2020are 600 tonnes.

The Company recorded a net loss of $7.0 millionin Q2 2020 following the recognition of a deferred income tax expense of $1.5 million. This compares to net loss of $15.3 millionin Q2 2019 and is primarily due to a decrease in operating and finance costs but was partially offset by a decrease in revenues and interest income, and an increase in the foreign exchange loss during the quarter.

The Company's trade payables balance at June 30, 2020with its former off-take partner was $2.4 million. The decrease is primarily attributable to the payment made of approximately $57.4 millionduring Q2 2020 and the balance at June 30, 2020is attributable to the re-measurement of trade receivables / payables for V2O5sold in the period to April 30, 2020. The Company anticipates that the final re-measurement of trade receivables / payables resulting from its recently terminated offtake agreement will negatively impact future periods by an aggregate of approximately $0.3 million.

Operating costs for Q2 2020 were $9.6 millioncompared to $24.8 millionin Q2 2019 and include direct mine and mill costs of $2.2 million($16.8 millionin Q2 2019), royalties of $1.3 million, product acquisition costs of $2.4 million, distribution costs of $0.3 million, inventory write-down of $1.3 millionand depreciation and amortization of $2.0 million. The decrease in direct mine and mill costs is primarily attributable to the decrease in V2O5equivalent sold in Q2 2020.

Cash operating costs excluding royalties3in Q2 2020 were $1.89per lb sold compared to $3.34in Q2 2019. The measure for Q2 2020 includes the benefit of tax credits of $2.2 million, without which the cash operating costs excluding royalties3per lb would be $3.04. The decrease seen in Q2 2020 compared with Q2 2019 is largely due to the decreased sales as noted previously. For Q2 2020, total cash costs3were $3.68(the measure for Q2 2020 includes the benefit of tax credits of $2.2 million, without which the total cash costs3would be $4.66). Total cash costs3exclude royalties and include the Company's total professional, consulting and management fees and other general and administrative expenses.

Cash (used in) provided by operating activities decreased from cash provided in Q2 2019 of $22.3 millionto cash used in Q2 2020 of $63.6 million. This is primarily due to the change in accounts payable of $51.4 millionin Q2 2020 when a payment was made to reduce the Company's trade payables balance with its former off-take partner. A further factor is the change in inventory of $15.9 millionin Q2 2020 as a consequence of the increased time for the Company to deliver its products and recognize sales as well as the building of strategic stock levels.

Second Quarter 2020 Operational Results

Total production from the Maracás Menchen Mine was 2,562 tonnes of V2O5, representing an increase of 2.0% over Q2 2019. Following the completion of the Company's preventative maintenance program, V2O5production in April 2020was 480 tonnes with 1,052 tonnes produced in May 2020and 1,030 tonnes in June 2020.

In Q2 2020, 257,357 tonnes of ore were mined with an effective grade6of 1.20% of V2O5. The Company produced 99,059 tonnes of concentrate with an effective grade6of 3.20%. The decrease in total ore mined when compared to Q2 2019 is due to operational adjustments to limit the mine site contractor workforce during the COVID-19 pandemic as well as operational restrictions due to the rainy season. The Company used available stocks to feed the crushing plant in order to mitigate the impact on V2O5production.

The Q2 2020 global recovery2of 80.8% was higher than both Q2 2019 (79.1%) and the budget, with strong recovery levels seen in both the kiln and leaching areas of the plant.

The Company's planned upgrades to the kiln and improvements in the cooler have been postponed until Q4 2020 as a result of precautionary measures such as limiting mine site personnel and contractors in light of the COVID-19 pandemic. This work is intended to increase the nameplate capacity to 1,100 tonnes of V2O5per month and is not expected to have a significant impact on the Company's Q4 2020 production.

2020 Vanadium Sales Progress In-Line with Expectations – 2020 Guidance Maintained

The Company completed its first independent shipment of vanadium from Brazilon May 14, 2020to an end-user in the U.S. Since then, the Company has delivered both standard grade and high purity V2O5 as well as ferrovanadium ("FeV") to customers in Brazil, North America, Europeand Asia. The Company's logistics operations have experienced some cancelations and delays related to COVID-19, both inside and outside of Brazil. The Company has, so far, been able to fulfil all of its commercial commitments with on-time deliveries thanks to careful planning and responsiveness. Largo maintains its 2020 sales, cost and production guidance and will continue to monitor the rapidly developing impacts of the COVID-19 pandemic, taking all possible actions to help minimize the impact on the Company and its people. However, these actions could significantly change the guidance and forecasts presented and Largo will, if and when necessary, update its guidance accordingly.

The markets in which the Company operates have also seen impacts in various ways during Q2 2020. COVID-19 had a negative impact on the demand for vanadium from the aerospace industry while on the positive side, the Chinese steel sector, which currently accounts for approximately 50% of the total global vanadium demand, saw a sharp recovery. During Q2 2020, the Chinese V2O5price increased approximately 15% ending the period at an average V2O5price per lb of $6.95. Additionally, the average price per lb of V2O5in Europedecreased by 5%, ending the period with an average price of approximately $5.30, compared with approximately $5.58at March 31, 2020. The average price per lb of V2O5for Q2 2020 was approximately $6.14, compared with approximately $8.59for Q2 2019. Largo is now selling products with pricing based on several different V2O5and FeV benchmarks and the Company's revenues will be driven by the movements in these prices.

Vanadium: The Green Metal – 2019 Sustainability Report

The Company announced the release of its 2019 sustainability report on July 20, 2020, highlighted by improved performance metrics and new reporting standards. This report is guided in part by SASB, the Sustainability Accounting Standards Board. The Company's new approach to sustainability reporting sets a new standard for open and transparent communication and Largo expects to continually improve its disclosures in the years to come. The report is available for download within the Responsibility section of the Company's website at www.largoresources.com/responsibility-page.

2020 Drill Program Underway

The Company's 2020 drill program recommenced in late June 2020following delays caused by the COVID-19 pandemic. All drilling personnel have followed the prescribed COVID-19 quarantine procedures before beginning work on site and Largo does not anticipate any further disruptions to the overall plan going forward. Additional drill equipment and crews were mobilised in July and August 2020to increase the production of total metres drilled in order to maintain the planned drilling timeframes at the various targets.

The Company has planned for 22,500 metres of drilling on the Near Mine Targets in 2020, primarily to upgrade and expand known resources to determine initial mining opportunities. Additional drilling (7,500 metres) has been planned in and around the Campbell pit to test for down dip continuations of known mineralisation. Mineralisation at the Campbell pit remains open at depth based on current drill results and exploration on the South Block will include a soil geochemistry sampling survey and 9,600 metres of drilling on higher priority targets based on geological, geophysical and geochemical data. As of August 11, 2020, the Company had completed 3,725 metres of drilling in 17 holes at the Novo Amparo Norte deposit and will shortly begin drilling at the Gulçari A Norte deposit.

TiO2 Pigment Project: Ilmenite and TiO2Chemical Pilot Plants in Progress to Develop TiO2Pigment

The Company continues its work on advancing basic engineering studies to further evaluate the economics associated with upgrading the non-magnetic tailings using concentrate flotation to produce titanium ("TiO2") concentrate for the pigment industry. The ilmenite chemical pilot plant was completed in October 2019and was proven successful with ilmenite product being produced shortly after. The Company constructed an additional chemical pilot plant to further upgrade its ilmenite product to TiO2pigment in April 2020. Test work to further understand and evaluate the Company's TiO2chemical pilot plant product is ongoing.

Conference Call

Largo Resources' management will host a conference call on Friday, August 14, 2020, at 2:00 p.m. ET, to discuss both operational and financial results for the second quarter of 2020.

_Conference Call Details:__ _

| Date: | Friday, August 14, 2020 | | Time: | 2:00 p.m. ET | | | | | Dial-in Number: | Local / International: +1 (416) 764-8688 | | | North American Toll Free: (888) 390-0546 | | | Brazil Toll Free: 08007621359 | | Conference ID: | 63772474 | | | | | Replay Number: | Local / International: + 1 (416) 764-8677 | | | North American Toll Free: (888) 390-0541 | | | Replay Passcode: 772474 # | | Website: | To view press releases or any addition al financial information, please visit our Investor Relations section of the Largo Resources website at:www.largoresources.com/investors |

A playback recording will be available on the Company's website for a period of 60-days following the conference call.

The information provided within this release should be read in conjunction with Largo's unaudited condensed interim consolidated financial statements for the three and six months ended June 30, 2020and 2019 and its management's discussion and analysis for the three and six months ended June 30, 2020, which are available on our website at www.largoresources.comand on SEDAR.

About Largo Resources

Largo Resources is an industry preferred producer and supplier of vanadium for the global steel and high purity markets. Largo's VPURE™ and VPURE+™ products are sourced from one of the world's highest-grade vanadium deposits at the Maracás Menchen Mine located in Brazil. The Company's common shares are principally listed on the Toronto Stock Exchange under the symbol "LGO". For more information on Largo and VPURE™, please visit www.largoresources.comand www.largoVPURE.com.

Neither the Toronto Stock Exchange (nor its regulatory service provider) accepts responsibility for the adequacy or accuracy of this release.

Forward Looking Information

This press release contains forward-looking information under Canadian securities legislation, some of which may be considered "financial outlook" for the purposes of application Canadian securities legislation ("forward-looking statements"). Forward–looking information in this press release includes, but is not limited to, statements with respect to the timing and amount of estimated future production and sales; costs of future activities and operations; the extent of capital and operating expenditures; and the extent and overall impact of the COVID-19 pandemic in Braziland globally. Forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". All information contained in this news release, other than statements of current and historical fact, is forward looking information. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Largo to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Largo and in its public documents filed on SEDAR from time to time. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. Although management of Largo has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Largo does not undertake to update any forward-looking statements, except in accordance with applicable securities laws. Readers should also review the risks and uncertainties sections of Largo's annual and interim MD&As which also apply.