i-80 Gold Corp. press release

/C O R R E C T I O N from Source -- i-80 Gold Corp/

TSX - Toronto Stock Exchange · Gold · Silver · United States

Canada NewsWire

In the news release, i-80 Gold Announces Positive Updated Preliminary Economic Assessment on the Cove Project, Nevada ; After-Tax NPV(5%) of $271 Million with an After-Tax IRR of 30% at US$2,175 /oz Au, issued 12-Feb-2025 by i-80 Gold Corp over PR Newswire, we are advised by the company that they wish to add a correction as to the nature of the release as a sub-headline, with an updated headline. The complete, corrected release follows:

Correction to i-80 Gold's Announcement of Positive Updated Preliminary Economic Assessment on the Cove Project, Nevada; After-Tax NPV(5%) of $271 Million with an After-Tax IRR of 30% at US$2,175/oz Au

This news release is being republished to confirm that it constitutes a designated news release for the purpose of the Company's prospectus supplement dated August 12, 2024 to its short form base shelf prospectus dated June 21, 2024 . The complete, corrected press release follows:

This news release constitutes a "designated news release" for the purposes of the Company's prospectus supplement dated August 12, 2024 , to its short form base shelf prospectus dated June 21, 2024 .

RENO, Nev. , Feb. 12, 2025 /CNW/ - i-80 GOLD CORP. (TSX: IAU) (NYSE: IAUX) ("i-80 Gold", or the "Company") is pleased to announce the results of an updated preliminary economic assessment (the "2025 PEA" or the "Study") for the Cove Project ("Cove" or the "Project"), an advanced underground exploration project located on the Battle Mountain-Eureka Trend in Northern Nevada , United States . The 2025 PEA confirms that the high-grade Cove Project has the potential to become a key component of the Company's regional "hub-and-spoke" mining and processing strategy.

The 2025 PEA replaces the previous PEA for the Project completed in 2021 (the "2021 PEA"). The Study has been updated to reflect a remodeling of the deposit using a more confined mining geometry, further advancement of the hydrology model, as well as using updated precious metals prices, capital and operating costs. All amounts are in United States dollars, unless otherwise stated.

"The 2025 PEA for the Cove Project represents an important first step in delivering updated technical information across i-80 Gold's asset portfolio. The results validate our planned regional hub-and-spoke model of feeding a central processing plant with high-grade material from three underground mines, which is expected to form the production base for i-80 Gold moving forward. In the coming weeks, we look forward to releasing updated PEAs for Granite Creek (both open pit and underground) and the Ruby Hill Complex (Archimedes underground and Mineral Point open pit)," stated Richard Young , Chief Executive Officer of i-80 Gold.

2025 PEA Highlights

Mineral Estimates, Production and Mine Life

Underground gold mine with a life of mine ("LOM") of approximately 8 years. Average annual gold production of approximately 100,000 ounces of gold following ramp up. Estimated LOM cash costs (1) of $1,194 per ounce and all-in-sustaining costs (1) of $1,303 per ounce. Updated mineral resource estimate resulting in an indicated gold mineral resource of 311,000 oz at 8.2 grams per tonne ("g/t") and an inferred gold mineral resource of 1.16 Moz at 8.9 g/t. The current infill drill program conducted over the past two years is not included in the 2025 PEA, however, all drill results will be included in the feasibility study targeted for completion in the fourth quarter 2025. Several underground exploration targets to be followed up in the coming years to potentially extend the mine life beyond the current 8 years.

Project Economics

Based on a $2,175 /oz gold price, the Project's undiscounted after-tax cash flows (2) total $397 million with an after-tax net present value ("NPV") of $271 million (2) , assuming a 5% discount rate, generating a30% internal rate of return ("IRR"). Based on a spot gold price of $2,900 /oz, the Project's undiscounted after-tax cash flows (2) total $793 million with an after-tax NPV of $582 million (2) , assuming a 5% discount rate, generating a IRR of 52%. Mine Construction capital estimated at $157 million , nearly 60% of which is earmarked for dewatering activities. LOM sustaining capital estimated to total $49 million . All operating, processing, pre-production, mine construction, and sustaining costs have been updated relative to the 2021 PEA to reflect current market pricing.

Mining and Processing

Mining to use a combination of cut-and-fill and bench-and-fill methods unchanged from the previous study. Nearly 60% of the material mined is anticipated to be processed at i-80 Gold's Lone Tree autoclave facility (see Figure 3) and the remainder processed at a third-party roasting facility with whom the Company has an established contract. Average gold grade processed of 10.4 g/t with an average gold recovery of 86% (autoclave) and 79% (roaster). A summary of key valuation, cost, and operating metrics is presented in Table 1 below. For more detailed metrics presented on an annual basis, see Cove Project Detailed Cash Flow Model in Appendix.

Table 1: Summary of 2025 PEA Key Operating and Financial Metrics

| Project Economics | Unit | | | Gold Price | $/oz | $2,175 | | Silver Price | $/oz | $27.25 | | Pre-Tax NPV (5%) (2) | $M | $337 | | After-Tax Cash Flow (2) | $M | $397 | | After-Tax NPV (5%) (2) | $M | $271 | | After-Tax IRR | % | 30 % | | Production Profile | | | | Mine Life | years | 8 | | Mineralized Material Mined | 000s tonnes | 2,675.6 | | Gold Grade of Mineralized Material Mined | g/t Au | 10.4 | | Silver Grade of Mineralized Material Mined | g/t Ag | 6.2 | | Waste Tonnes Mined | 000s tonnes | 226.1 | | Total Tonnes Mined | 000s tonnes | 2,901.8 | | Total Mineralized Material Processed | 000s tonnes | 2,675.6 | | Gold Grade Processed | g/t Au | 10.4 | | Silver Grade Processed | g/t Ag | 6.2 | | Average Gold Recovery | % | 83 % | | Average Silver Recovery | % | 24 % | | Total Gold Recovered | 000s oz | 739.6 | | Total Silver Recovered | 000s oz | 114.5 | | Average Annual Gold Production (LOM) | 000s oz | 92.4 | | Average Annual Gold Production (following production ramp up) | 000s oz | 100 | | Unit Operating Costs | | | | LOM Operating Cost | | | | Mineralized Material Mined | $/t | 142.2 | | Mineralized Material and Waste Mined | $/t | 141.0 | | Processed | $/t milled | 80.0 | | Transportation Costs | $/t milled | 20.8 | | Electricity Dewatering | $/t milled | 26.5 | | G&A | $/t milled | 21.5 | | LOM Total Cash Costs (1) (net of by-product credit) | $/oz | $1,194 | | LOM All-in Sustaining Costs (1) (net of by-product credit) | $/oz | $1,303 | | Total Capital Costs | | | | Pre-Development Capital | $M | $17.3 | | Construction Capital | $M | $157.4 | | LOM Sustaining Capital | $M | $49.1 | | Closure Costs | $M | $31.3 | | Total Capital & Closure Costs (3) | $M | $255.1 |

"The Study highlights the value Cove brings to our gold portfolio, showcasing high-grade mineralization on a brownfield site in a top-tier mining jurisdiction, with low capital requirements and a high return on invested capital," added Matthew Gili , President and Chief Operating Officer of i-80 Gold. "The Study primarily updates the 2021 PEA's economic model and includes findings from hydrological studies, which have increased our understanding of the Project's dewatering needs. Additionally, the completion of an exploration decline has enabled infill resource drilling and advanced metallurgical test work, which will be included in a feasibility study planned for the fourth quarter of 2025."

Mineral Resource Update

The 2025 PEA is based on a revised resource model with no additional drilling results included, relative to the 2021 PEA. The updated resource estimate has been calculated using stope optimizer software, whereas the previous mineral resource was not. The new methodology generates optimal mineable stope geometries while considering several factors including geological constraints, grade distribution and stope dimensions. This significantly improves the accuracy of mineral resource estimates and has become an industry standard for underground deposits in Nevada .

The updated mineral resource estimate includes a total of 311,000 ounces of gold at 8.2 g/t Au in the indicated category and 1,156,000 ounces of inferred resources at 8.9 g/t in the inferred category (see Table 2). The majority of the indicated resource is currently hosted in the Helen deposit (see Figure 1). The updated estimate resulted in additional mineralized body constraints resulting in indicated and inferred tonnes decreasing by 6% and 13% respectively. Moreover, gold ounces decreased by 20% in the indicated and inferred categories, however the updated mineral resource represents more mineable shapes than the prior resource estimate.

The ongoing Cove drilling program has been designed to infill mineralization in the Helen and Gap zones ahead of a planned feasibility study in 2025. The Project offers substantial exploration potential as the bulk of the work completed to date has been focused on the main deposit areas only. Exploration from 2014 through 2019 resulted in the identification of several new zones of mineralization that have received minimal follow-up, including mineralization in the 2201 zone (153,000 tonnes at 26.7 g/t Au) beneath the Cove pit (see Figure 1).

[](https://mma.prnewswire.com/media/2619054/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Table 2: Cove Mineral Resource Estimate as at December 31, 2024

| | Indicated Mineral Resources | | | | | | | | Tonnes | Au | Ag | Au | Ag | | | | (000) | (g/t) | (g/t) | (000 oz) | (000 oz) | | | Helen | 674 | 9.3 | 2.6 | 201 | 55 | | | Gap | 254 | 7.5 | 8.9 | 61 | 72 | | | CSD | 249 | 6.0 | 55.0 | 48 | 441 | | | Total Indicated | 1,178 | 8.2 | 15.0 | 311 | 569 | | | | | | | | | | | | Inferred Mineral Resources | | | | | | | | Tonnes | Au | Ag | Au | Ag | | | | (000) | (g/t) | (g/t) | (000 oz) | (000 oz) | | | Helen | 1,582 | 8.4 | 2.9 | 427 | 146 | | | Gap | 2,022 | 8.4 | 9.0 | 543 | 585 | | | CSD | 290 | 5.9 | 57.8 | 55 | 538 | | | 2201 | 153 | 26.7 | 34.8 | 131 | 171 | | | Total Inferred | 4,046 | 8.9 | 11.1 | 1,156 | 1,439 | |

| Notes to table above: | | | I. | Mineral resources have been estimated at a gold price of $2,175 per troy ounce and a silver price of $27.25 per troy ounce; | | II. | Mineral resources have been estimated using gold metallurgical recoveries ranging from 73.2% to 93.3% for roasting and 78.5% to 95.1 % for pressure oxidation; | | III. | Roaster cutoff grades range from 4.15 to 5.29 Au g/t (0.121 to 0.154 opt) and pressure oxidation cutoff grades range from 3.83 to 4.64 Au g/t (0.112 to 0.135 opt); | | IV. | The effective date of the mineral resource estimate is December 31, 2024; | | V. | Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant factors; | | VI. | An inferred mineral resource is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred mineral resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration; and | | VII. | The reference point for mineral resources is in situ. |

Economic Analysis

Cove's NPV and IRR in relation to fluctuations in the long-term gold price are demonstrated in Table 3 and the Project's cost sensitivities are illustrated in Figure 2 below.

Table 3: Cove Project Gold Price Sensitivity After-tax Analysis

| | Gold Price ($/oz) | | | | | | | | | $1,850 | $2,000 | $2,175 | $2,500 | $2,750 | $2,900 | $3,000 | | NPV 5% (2) ($M) | $134 | $198 | $271 | $409 | $516 | $582 | $626 | | IRR (%) | 19 % | 24 % | 30 % | 40 % | 47 % | 52 % | 54 % |

[](https://mma.prnewswire.com/media/2619055/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Project Overview

The Project is located 25 miles southwest of the town of Battle Mountain , in the McCoy mining district in the Fish Creek Mountains of Lander County, Nevada (see Figure 3). The Cove deposit was mined by Echo Bay Mines Ltd. ( Echo Bay ) between 1988 and 2000 during which period the Cove deposit produced 2.6 million ounces of gold and 100 million ounces of silver. Gold and silver production from heap leach pads continued until 2006. The Project benefits from extensive historical geological datasets, its location in a jurisdiction with deep mining pedigree, and access to both local and regional infrastructure, including proximity to paved highways, electrical power, pre-existing mine infrastructure, and a skilled labor force.

i-80 Gold's predecessor purchased the Cove project in 2012 and has since conducted significant exploration and infill drilling, metallurgical testing, and has advanced the permitting process. The Company expects to begin expending development capital, primarily for dewatering activities in late 2027 or early 2028 and for production to ramp up during 2029.

[](https://mma.prnewswire.com/media/2619056/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Geology and Mineralization

The Cove deposit consists of Helen, Gap, CSD, and 2201 zones. They are located beneath the historically mined Cove open pit and extend approximately 2,000 feet northwest from the pit (see Figure 1). The current mine plan includes Helen and Gap while CSD and 2021 could be included in a future mine plan, subject to the completion of additional technical work.

Three main types of mineralization occur at Cove. The Helen and Gap zones are Carlin-style disseminated refractory gold deposits. The Cove South Deep (CSD) gold and silver mineralization is similar in character to that at Helen and Gap but is characterized by silver to gold ratios of 50:1 to over 100:1. The 2201 zone is comprised of disseminated sulfides within sheeted stockwork veins and massive sulfide lenses replacing carbonate. Both styles of mineralization in the 2201 zone contain locally high concentrations of lead and zinc in addition to gold and silver. Structural controls on mineralization include the broad, gently southeast-plunging Cove anticline, several northeast striking dike-filled normal faults (Cay, Blasthole, Bay, 110, Gold Dome), mafic sills, and rheology contrasts.

Although most well-known Carlin -type deposits are hosted in Paleozoic slope and shelf carbonates, host rocks at Cove are silty to massive limestones and dolomites of the Triassic Star Peak Group. Limestone and silty limestone of the Favret Formation (approximately 700 feet thick) are the primary host for Carlin-style mineralization, and the Dixie Valley Formation conglomerates are the primary host of polymetallic vein mineralization in the 2201 zone.

Mining and Processing

The Study demonstrates an initial 8-year mine life with average annual gold production of approximately 100,000 ounces of gold following ramp up. The Study represents a preliminary point-in-time estimate of the mine plan. Once underground infrastructure is constructed a significant exploration program is planned to follow up on earlier positive drill results in a more cost-effective manner with a goal of extending the mine life beyond the current 8 years.

The high-grade mine will be accessed by a single ramp extending from the surface (elevation 4,625 ft) to the lowest extent of planned mining (elevation 3,430 ft). The access ramp will be large enough to accommodate 30-ton trucks. A series of raises will provide secondary egress and ventilation. A mining contractor will extract the mineralization using drift and fill mining methods at an average rate of approximately 1,100tonnes per day.

Metallurgical testing has demonstrated that both Helen and Gap resources are generally refractory and require an oxidation process to increase gold extraction using whole cyanidation of mineralized material. Composite testing has shown that Helen samples are generally more amenable to roasting and carbon-in-leach ("CIL") processing, while the Gap zone is more amenable to an autoclave process followed by CIL. Upon the commencement of mining and processing, a detailed and systematic mineralized material control sampling program will be utilized to determine which of the two facilities (roaster vs. autoclave) the material should be routed to, to maximize recovery rates.

The PEA incorporates toll-milling arrangements with associated over-the-road trucking costs for both process streams. The PEA contemplates the use of the Lone Tree autoclave (owned by the Company and in respect of which an autoclave refurbishment class 3 engineering study is expected to be completed in 2025) and a third-party roaster for which a toll-milling agreement has been negotiated for the treatment of that material.

[](https://mma.prnewswire.com/media/2619057/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Capital Cost Summary

Mine construction capital is estimated to be $157.4 million . Approximately 60% of capital expenditures is for dewatering activities with the balance to be used for portal and underground development to gain access to the mineralized bodies (see Table 4). The low development capital required to construct Cove is due in part to the existence of significant infrastructure, including a portal to the Helen deposit and 5,739 feet of development work already completed. Permitting activities are well underway (see _Permitting _section for more detail). The permitting process is expected to take approximately three years to complete followed by 18 months of construction which is primarily dewatering and underground development, as well as some light surface infrastructure work.

Cove is expected to generate an estimated $379 million in net cash flow over the current 8-year mine life (see Figure 5).

Table 4: Capital Cost Estimates

| | Pre- Development | Mine Construction | Sustaining | | ($M) | ($M) | ($M) | | | Environmental, Permitting and Feasibility | $7.0 | - | - | | Dewatering - Helen | - | $39.5 | - | | Dewatering - Gap | - | $48.4 | - | | Electrical Service and Powerline | - | $10.5 | - | | Mine Development - Helen | - | $24.8 | $21.0 | | Mine Development - Gap | - | $0.4 | $20.3 | | Mine Facilities | - | $2.2 | $1.3 | | Pre-production Expense | $5.0 | $3.6 | - | | Resource Conversion Drilling | $2.0 | - | - | | Contingency (15% Drilling and Development; 25% Facilities) | $3.3 | $28.0 | $6.5 | | Total Capital Cost (3) | $17.3 | $157.4 | $49.1 |

[](https://mma.prnewswire.com/media/2619058/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Operating Cost Summary

The 2025 PEA estimates a cash cost(1) of $1,194 per ounce of gold and an all-in sustaining costs(1) of $1,303 per ounce of gold for the LOM (see Table 5). Figure 6 illustrates these operating costs over Cove's estimated production profile.

Table 5: Total and Unit Operating Costs

| | Total Costs | Unit Cost | Cost per Ounce | | ($M) | ($/t milled) | ($/oz Au) | | | Mining | $408 | $152 | $552 | | Transportation & Processing | $270 | $101 | $365 | | Electrical Power | $71 | $26 | $96 | | G&A, Royalties & Net Proceeds Tax | $138 | $51 | $186 | | By-Product Credits | ($3) | ($1) | ($4) | | Total Operating Cost/Cash Cost | $883 | $330 | $1,194 | | Closure & Reclamation | $31 | $12 | $42 | | Sustaining Capital | $49 | $18 | $66 | | All-in Sustaining Costs (1) | $963 | $360 | $1,303 |

[](https://mma.prnewswire.com/media/2619059/i_80_Gold_Corp_Correction_to_i_80_Gold_s_Announcement_of_Positiv.html)

Permitting

National Environmental Policy Act (NEPA) associated permitting activities continue to progress with all baseline study reports and the Plan of Operations Amendment having been submitted to the Bureau of Land Management (BLM). The permitting action is anticipated to require a Notice of Intent to Complete an Environmental Impact Statement (EIS). Following the EIS notification process, a public scoping period will be completed and a draft EIS will be prepared and subsequently posted for public review and comment. The public comments and associated responses will be incorporated into the Final EIS document for BLM acceptance.