Centerra Gold's Mount Milligan PFS Outlines Mine Life to 2045, Delivering Growth with a Fully Funded, Disciplined $186 Million Growth Capital Plan

TSXV - TSX Venture Exchange · Gold · Silver · Copper · Zinc · Antimony · Lithium · Cesium · Rubidium · Gallium · Tin · Nickel · Platinum · Palladium · Platinum Group Metals · Cobalt · Molybdenum · Rare Earth Elements · Tungsten · Canada

Centerra Gold’s Mount Milligan PFS Outlines Mine Life to 2045, Delivering Growth with a Fully Funded, Disciplined $186 Million Growth Capital Plan

This news release contains forward-looking information about expected future events that is subject to risks and assumptions set out in the “Cautionary Statement on Forward-Looking Information” below. All figures are in United States dollars unless otherwise stated. All production figures reflect payable metal quantities and are on a 100% basis, unless otherwise stated. For references denoted with NG, refer to the “Non-GAAP Financial Measures” disclosures at the end of this news release for a description of these measures.

TORONTO, Sept. 11, 2025 (GLOBE NEWSWIRE) -- Centerra Gold Inc. (“Centerra” or the “Company”) (TSX: CG) (NYSE: CGAU) is pleased to announce the results of a Pre-Feasibility Study (“PFS”) for its Mount Milligan mine (“Mount Milligan”) in British Columbia, confirming a life of mine (“LOM”) extension of approximately 10 years, to 2045. The extension is driven by disciplined future investments, including increasing process plant capacity in 2029 and constructing a second tailings storage facility (“TSF”) in the first half of the 2030s. These initiatives reinforce Mount Milligan as a long-term, low-cost contributor to Centerra’s production profile and cash flow generation in a top tier mining jurisdiction.

President and CEO, Paul Tomory, commented, “Mount Milligan’s LOM extension marks a key milestone in advancing Centerra’s organic gold growth strategy. Recent step-out and infill drilling programs have confirmed the continuation of mineralization to the west of the current open pit. Incorporating this drilled inventory, the PFS outlines a 10-year LOM extension, to 2045, supported by phased, manageable non-sustaining capital expenditures NG totaling $186 million, most of which is not required until the early-to-mid-2030s, that we expect to fully fund from available liquidity. The PFS reaffirms Mount Milligan’s solid economics, underpinned by consistent production, disciplined capital deployment, and low all-in sustaining costs on a by-product basis NG . As we look to the future of Mount Milligan, we are encouraged by the establishment of British Columbia’s new Mining and Critical Minerals Ministry and by Mount Milligan’s designation as a provincial priority project, in support of a more streamlined permitting process. Ongoing exploration continues to highlight the potential to further expand mineral resources and extend mine life beyond the updated plan. Mount Milligan remains a strategic cornerstone asset in Centerra’s portfolio, with 20 years of mine life, meaningful low-cost gold and copper production, strong cash flow generation, and significant opportunity for future exploration potential in a top tier mining jurisdiction.”

Mount Milligan PFS Highlights

LOM Extension and Optimized Mine Plan: The PFS indicates the extension of the LOM by approximately 10 years, to 2045, supported by an optimized mine plan. The average annual production from 2026 to 2042, is expected to be approximately 150,000 ounces of gold and 69 million pounds of copper, followed by the processing of low-grade stockpiles from 2043 to 2045. Disciplined, Fully Funded, Low Capital Investment: Approximately $186 million in non-sustaining capital expenditures NG are planned, most of which are not required until the early-to-mid-2030s, all fully funded from available liquidity and future cash flow from operations. Key investments include $114 million for a second TSF to be spent across 2032 and 2033, $36 million for ball mill motor upgrades and flotation cells in 2028 to increase process plant throughput by about 10% to 66,300 tonnes per day (“tpd”) and increase recovery by approximately 1%, and $28 million for five new haul trucks to support longer haul distances, higher material movement, and stockpile development. The planned second TSF also provides the potential for future raises, which could add multiple decades of storage capacity beyond the 2045 LOM. Significant Increase in Mineral Reserves: An updated proven and probable mineral reserve totalling 483.2 million tonnes, with an average grade of 0.28 grams per tonne (“g/t”) gold and 0.16% copper, containing 4.4 million ounces of gold and 1.7 billion pounds of copper was included in the PFS. This represents a 56% increase from the 2.8 million ounces of gold reserves and a 52% increase from the 1.2 billion pounds of copper reserves reported at the end of 2024, driven mainly by resource conversion related to increased tailings capacity and infill drilling. Strong Exploration Upside: Recent drilling confirms mineralization remains open to the west of the current resource pit. Centerra plans to continue exploring with a focus on expanding the mineral resource and evaluating opportunities to extend the mine life beyond the updated plan. Robust Economics: The PFS reaffirms Mount Milligan’s solid economics, supported by consistent production, disciplined capital investment and low all-in sustaining costs (“AISC”) on a by-product basis NG . Mount Milligan’s after-tax NPV (5%) (“NPV 5% ”) is approximately $1.5 billion, based on long-term gold and copper price assumptions of $2,600 per ounce and $4.30 per pound, respectively. At spot commodity prices of approximately $3,500 per ounce of gold and $4.50 per pound of copper, the after-tax NPV 5% increases to approximately $2.1 billion. For additional detail, refer to “Summary of Mount Milligan PFS Key Metrics” table and footnotes below. Cornerstone Asset Driving Long-Term Value: Mount Milligan remains a strategic cornerstone asset in Centerra’s portfolio, with 20 years of mine life, meaningful gold and copper production, strong cash flow generation, and significant opportunity for future exploration potential in a top tier mining jurisdiction.

Summary of Mount Milligan PFS Key Metrics

| Summary of Mount Milligan PFS Key Metrics | | | Production | | | Mine Life (years) | 20 | | Total gold production (kozs) | 2,791 | | Average annual gold production – 2026-2042 (1) (kozs) | 150 | | Average annual gold production – LOM (kozs) | 136 | | Total copper production (Mlbs) | 1,282 | | Average annual copper production – 2026-2042 (1) (Mlbs) | 69 | | Average annual copper production – LOM (Mlbs) | 63 | | Total mill feed (M tonnes) | 483 | | Average mill throughput ( 2) (tpd) | 66,300 | | Average gold grade – 2026-2042 (1) (g/t) | 0.31 | | Average gold grade – LOM (g/t) | 0.28 | | Average copper grade – 2026-2042 (1) (%) | 0.18 | | Average copper grade – LOM (%) | 0.16 | | Average gold recovery (%) | 64.8 | | Average copper recovery (%) | 78.0 | | Costs | | | Mining cost per tonne mined ( 3 ) ($/tonne) | 2.50 | | Processing cost per tonne processed ($/tonne) | 5.57 | | General & Administrative (“G&A”) cost per tonne processed ( 4) ($/tonne) | 2.11 | | Gold production costs per ounce sold ($/oz) | 1,312 | | All-in sustaining costs on a by-product basis NG per ounce sold ($/oz) | 950 | | Capital Expenditures | | | LOM Total capital expenditures NG ($ millions) | 925 | | Non-sustaining capital expenditures NG ($ millions) | 186 | | Sustaining capital expenditures NG ( 8) ($ millions) | 739 | | PFS Economics ( 5 , 7 ) | | | After-tax NPV 5% ($ millions) | 1,492 | | Economics at Spot Commodity Prices ( 6 , 7 ) | | | After-tax NPV 5% ($ millions) | 2,127 |

(1) Averages reflect production and grades for 2026-2042. The period from 2043 to 2045 has been excluded, as it represents low-grade stockpile processing. (2) Average mill throughput starting in 2030 and beyond. (3) On the basis of gross mining costs, prior to the allocation to TSF, divided by total tonnes mined. (4) Excludes corporate allocations. (5) PFS economics are based on commodity prices of $3,205/oz gold and $4.35/lb copper in H2 2025, $3,263/oz and $4.48/lb in 2026, $3,078/oz and $4.60/lb in 2027, $2,928/oz and $4.67/lb in 2028, and a long-term assumption (2029+) of $2,600/oz gold and $4.30/lb copper. USD/CAD exchange rate assumptions are $1.39:1 in H2 2025, $1.38:1 in 2026, $1.37:1 in 2027, $1.36:1 in 2028 and $1.35:1 from 2029 onward. (6) Economics at spot commodity prices assumes $3,500/oz gold and $4.50/lb copper over LOM. All other assumptions are the same as the PFS economics. (7) After-tax NPV assumes amalgamation of various Canadian legal entities, including the subsidiary that owns Mount Milligan, to optimize tax deductions. (8) Does not include capital leases of $99M. Refer to PFS LOM Summary table at the end of this news release for more detail .

Mount Milligan PFS Summary

Centerra has completed a PFS for Mount Milligan that contemplates a 10-year LOM extension, to 2045, supported by an optimized mine plan, with average annual production, from 2026 to 2042, of approximately 150,000 ounces of gold and 69 million pounds of copper, followed by the processing of low-grade stockpiles from 2043 to 2045. Centerra’s recent infill drilling program, targeting tighter drill spacing in key areas of the deposit, has been incorporated into the PFS, improving confidence in the geology and mine plan.

Mount Milligan will continue to be mined as a conventional truck-shovel open pit mine. Total mining rates of ore and waste are expected to average 156 ktpd between 2026 and 2042. The strip ratio over the same period is expected to average 1.0. Mining will continue through 2042, at which time, lower grade stockpiles are expected to feed the process plant from 2043 through 2045.

Mine operations will incorporate in-pit dumping of potentially acid-generating (“PAG”) waste, reducing the environmental footprint, lowering operating costs, and optimizing tailings storage capacity. This approach reinforces Centerra’s commitment to delivering long-term value for all Mount Milligan stakeholders.

Operational improvements, including in-pit dumping and enhanced stockpile management, will increase efficiency as mining rates are expected to reach 200 ktpd at points during the LOM, requiring only a modest fleet expansion of five additional trucks. Regular equipment replacements and the five additional trucks will support the material movements for the remainder of the mine life.

In 2029, process plant throughput is expected to increase by 10%, from 60.0 ktpd to approximately 66.3 ktpd, by upgrading the ball mill motors. Flotation capacity is also expected to increase which should deliver a modest improvement in gold and copper recoveries of about 1%. These enhancements require a manageable capital investment of $36 million.

A second tailings facility is required to support the LOM expansion and is planned north of the existing facility, subject to consultation with First Nations, with an estimated cost of approximately $114 million, phased over 2032 and 2033. The new TSF is expected to deliver an improved water balance compared to the current facility, with subsequent lifts constructed using the capital-efficient cyclone sand method. The TSF footprint has been designed to accommodate future lifts, providing flexibility for potential further LOM extensions that could add multiple decades of capacity beyond the current mine life of 2045.

Over the LOM, open pit mining costs are expected to average $2.50 per tonne mined, processing costs are expected to average $5.57 per tonne processed, and G&A costs are expected to average $2.11 per tonne processed.

Mount Milligan PFS Production and Cost Profile ( 1)

(1) AISC on a by-product basis NG in 2030s is low due to higher copper credits in those years.

Royal Gold Additional Agreement

In February 2024, Centerra announced an additional agreement (the “Additional Agreement”) with RGLD Gold AG, a subsidiary of Royal Gold, Inc. (“Royal Gold”) related to Mount Milligan, which established favourable parameters for potential future mine life extensions. Under the Additional Agreement, the percentage of gold and copper production streamed to Royal Gold over the mine life remains unchanged at 35% and 18.75%, respectively. However, Centerra will receive increased payments for gold and copper sold to Royal Gold. Details of the Additional Agreement are illustrated in the tables below. For more information refer to the news release _“ Centerra Gold Announces Mount Milligan Mine Life Extension and Additional Agreement with Royal Gold ” _published on February 14, 2024.

Gold Stream

| Gold Delivery Threshold (after January 1, 2024) | Approximate Period ( 1) | Gold Payments Received from Royal Gold | | Until either 375,000 ounces of gold or 30,000 tonnes of copper have been delivered to Royal Gold (the “First Threshold”) | 2024 - 2029 | $435/oz | | After the First Threshold until 665,000 ounces of gold have been delivered to Royal Gold (the “Second Gold Threshold”) | 2030 - 2035 | Lower of $850/oz and 50% of spot gold price | | After 665,000 ounces of gold have been delivered to Royal Gold | 2036+ | Lower of $1,050/oz and 66% of spot gold price |

(1) Approximate period estimates are based on PFS production profile.

Copper Stream

| Gold Delivery Threshold (after January 1, 2024) | Approximate Period ( 1) | Gold Payments Received from Royal Gold | | Until either 375,000 ounces of gold or 30,000 tonnes of copper have been delivered to Royal Gold (the “First Threshold”) | 2024 - 2029 | 15% of spot copper price | | After the First Threshold until 60,000 tonnes of copper have been delivered to Royal Gold (the “Second Copper Threshold”) | 2030 - 2035 | 50% of spot copper price | | After 60,000 tonnes of copper have been delivered to Royal Gold | 2036+ | 66% of spot copper price |

(1) Approximate period estimates are based on PFS production profile.

Capital Expenditures NG

The total non-sustaining capital expenditures NG required for the Mount Milligan LOM extension is $186 million, mainly related to a second TSF, modifications in the process plant to increase throughput by approximately 10%, and five new haul truck additions. The capital program is designed to leverage existing infrastructure, reducing the cost and execution risk.

Approximately $36 million of non-sustaining capital NG is expected for the process plant expansion. Ball mill motor upgrades are expected to increase process plant throughput by approximately 10%, to 66.3 ktpd, reaching nameplate capacity in 2029. Flotation capacity is also expected to increase which should deliver a modest improvement in gold and copper recoveries of about 1%.

Approximately $114 million of non-sustaining capital NG is expected to be evenly distributed in 2032 and 2033 related to the second TSF. Sustaining capital for raises on the new TSF are expected to be more cost effective than the existing TSF construction method while maintaining high safety standards. After completion of the starter facility, the dam will be constructed using cycloned tailings sand produced by the process plant, offering efficiency and cost advantages compared to the existing earthen dam structure. This new facility, anticipated to be located to the north of the existing facility, subject to consultation with First Nations, would have the benefit of an improved water balance compared with the existing facility. The new TSF footprint is sufficiently large to enable future lifts that could potentially add multiple decades of capacity beyond the current mine life. Both designs follow the centerline construction method, a proven approach recognized for its geotechnical stability.

Approximately $28 million of non-sustaining capital NG is expected for fleet additions. This includes five new haul trucks, required to accommodate longer hauling distances, increased material movement to achieve higher process plant throughput, and the creation of strategic stockpiles.

In addition, sustaining capital NG of approximately $739 million is planned over the 20-year mine life, primarily allocated to ongoing equipment replacements, TSF raises, and other site infrastructure requirements.

A breakdown of the non-sustaining capital NG is included in the table below.

| Non-Sustaining Capital NG Breakdown | Total ($M) | | TSF Expansion | 114 | | Process Plant Expansion | 36 | | Fleet Additions | 28 | | Site Infrastructure | 7 | | Total Non-Sustaining Capital NG | 186 |

NOTE: Totals may not sum due to rounding.

Mineral Reserve and Mineral Resource Estimate

An updated proven and probable mineral reserve totalling 483.2 million tonnes, with an average grade of 0.28 grams per tonne gold and 0.16% copper, containing 4.4 million ounces of gold and 1.7 billion pounds of copper was included in the PFS. This represents a 56% increase from the 2.8 million ounces of gold reserves and a 52% increase from the 1.2 billion pounds of copper reserves reported at the end of 2024, driven by resource conversion related to increased tailings capacity. Mineral resources, inclusive of reserves, at Mount Milligan have increased following infill drilling at the western extension of the deposit. The Company has lowered its mining cost assumptions for mineral reserves and resources, reflecting load and haul efficiencies achieved through the ongoing site optimization program.

Mount Milligan Gold Mineral Reserve and Resources

| | June 30, 2025 | December 31, 2024 | | | | | | Tonnes (kt) | Grade (g/t Au) | Contained Metal (kozs) | Tonnes (kt) | Grade (g/t Au) | Contained Metal (kozs) | | | Mineral Reserves | | | | | | | | Proven | 190,315 | 0.31 | 1,880 | 187,961 | 0.34 | 2,056 | | Probable | 292,842 | 0.27 | 2,537 | 76,551 | 0.31 | 770 | | Proven and Probable | 483,157 | 0.28 | 4,417 | 264,512 | 0.33 | 2,826 | | Mineral Resources (inclusive of Mineral Reserves) ( 1) | | | | | | | | Measured | 363,982 | 0.28 | 3,309 | 291,187 | 0.30 | 2,835 | | Indicated | 310,110 | 0.27 | 2,661 | 176,323 | 0.29 | 1,622 | | Measured and Indicated | 674,092 | 0.28 | 5,970 | 467,510 | 0.30 | 4,457 | | Inferred Resources | 12,056 | 0.28 | 110 | 27,924 | 0.44 | 395 |

(1) Mineral resources inclusive of mineral reserves, as of December 31, 2024, is for comparative purposes only. See 2024 year-end mineral reserves and resources news release dated February 20, 2025, for mineral resources exclusive of mineral reserves as of December 31, 2024. NOTE: Refer to “Reserve and Resource Additional Footnotes” at the end of this news release. Totals may not sum due to rounding.

Mount Milligan Copper Mineral Reserve and Resources

| | June 30, 2025 | December 31, 2024 | | | | | | Tonnes (kt) | Grade (% Cu) | Contained Metal (Mlbs) | Tonnes (kt) | Grade (% Cu) | Contained Metal (Mlbs) | | | Mineral Reserves | | | | | | | | Proven | 190,315 | 0.17 | 698 | 187,961 | 0.19 | 808 | | Probable | 292,842 | 0.16 | 1,051 | 76,551 | 0.20 | 342 | | Proven and Probable | 483,157 | 0.16 | 1,749 | 264,512 | 0.20 | 1,150 | | Mineral Resources (inclusive of Mineral Reserves) ( 1) | | | | | | | | Measured | 363,982 | 0.17 | 1,378 | 291,187 | 0.19 | 1,212 | | Indicated | 310,110 | 0.14 | 979 | 176,323 | 0.18 | 703 | | Measured and Indicated | 674,092 | 0.16 | 2,357 | 467,510 | 0.19 | 1,915 | | Inferred Resources | 12,056 | 0.11 | 30 | 27,924 | 0.12 | 74 |

(1) Mineral inventory inclusive of mineral reserves, as of December 31, 2024, is for comparative purposes only. See 2024 year-end mineral reserves and resources news release dated February 20, 2025, for mineral resources exclusive of mineral reserves as of December 31, 2024. NOTE: Refer to “Reserve and Resource Additional Footnotes” at the end of this news release. Totals may not sum due to rounding.

Figure 1: Plan view comparing the 2024 reserve pit to the 2025 reserve pit. Gold areas illustrate the areas of expansion beyond the previous pit limits.

Exploration Potential

Exploration drilling in 2025 was completed in two phases. Phase 1 focused on upgrading inferred resources to the indicated category for inclusion in the PFS. Drilling was concentrated within the conceptual resource pit, with 83 holes totaling approximately 23 kilometres (“km”) completed and incorporated into the updated model. The Phase 1 program, completed in the first quarter of 2025, targeted Zone 66, GEF, Saddle, WBX, MBX, Southern Star and South Boundary.