Allied Critical Metals Inc. press release
Allied Critical Metals Further Highlights Rapid Payback, Capital Efficiency and Infrastructure from Borralha PEA
CSE - Canadian National Stock Exchange · Tungsten · Tin · Copper · Silver · Molybdenum · Zinc · Bismuth · Lead · Rare Earth Elements · Uranium · Thorium · Gold · Canada · Technical Studies
Allied Critical Metals Further Highlights Rapid Payback, Capital Efficiency and Infrastructure from Borralha PEA
After-tax NPV(8%) of $473M (US$346.6M) and 2.2-year payback from start of production with IRR of 48.8% at US$1,000/mtu WO3
Key Highlights:
Additional Payback Metrics: Payback1 of approximately 2.2 years from commencement of commercial production corresponding to approximately 4.2 years from start of construction under the medium / US$1,000/mtu WO₃2 case.
Capital Efficient Development: Initial capital cost3 of approximately $124.2 million (USD $91 million), with a compact infrastructure layout designed to support efficient underground mining and processing operations.
Strong Annual Cash Flow Generation: Average annual revenue of approximately $252,517 million (US$184,886 million), average annual EBITDA of approximately $142,181 million (US$104,101 million), and average annual free cash flow of approximately $96,279 million (US$70,493 million) over the initial mine plan at US$1,000/mtu WO₃.4
Integrated Infrastructure Design: Project infrastructure includes planned hydro electric power connection, water supply and recycling systems, road access, and paste backfill integration to support operations while minimizing environmental footprint.
Robust Core PEA Economics Maintained: Previously announced after-tax NPV(8%)5 of $473.4M (US$346.6 million) and IRR6 of 48.8% at US$1,000/mtu WO₃ remain unchanged.
Significant Upside Leverage: After-tax IRR of 78.4% and NPV(8%) of $963.8 million (USD $706.4 million) at USD $1,500/mtu WO₃.
Resource Growth Underway: Fully funded 20,000-metre drill program continues to target resource expansion, confidence conversion and potential mine life extension beyond the initial 11-year production plan, targeting resource expansion and confidence conversion.
All amounts in Canadian dollars unless stated otherwise.4
Vancouver, British Columbia--(Newsfile Corp. - March 9, 2026) - Allied Critical Metals Inc. (CSE: ACM) (OTCQB: ACMIF) (FSE: 0VJ0) ("Allied" or the "Company") is pleased to provide additional economic and technical detail from the recently announced Preliminary Economic Assessment ("PEA") for its 100%-owned Borralha Tungsten Project ("Borralha" or the "Project") in northern Portugal. The Project's previously announced PEA economics remain unchanged.
Roy Bonnell, CEO & Director of Allied, commented: "Following the release of our initial Borralha PEA, we received strong investor interest in additional project-level detail. This supplementary disclosure highlights the Project's capital efficiency, strong annual cash generation and well-developed infrastructure platform. Importantly, the underlying economics of the PEA remain unchanged, while the additional payback presentation provides another useful reference point for investors evaluating project returns and the strong leverage Borralha has to tungsten prices."
This additional disclosure provides greater clarity on Borralha's capital efficiency, expected cash flow generation and rapid capital recovery profile. The Borralha PEA outlines a capital-efficient underground tungsten development project within the European Union, demonstrating strong economic returns across a range of tungsten price assumptions and significant leverage to current market prices.
The Borralha PEA continues to demonstrate a technically robust and capital-efficient underground tungsten development project within the European Union. As previously announced, the PEA was evaluated under three pricing frameworks: the Base case of $962/mtu WO₃ (US$704/mtu WO₃), $1,365/mtu WO₃ (US$1,000/mtu WO₃), and $2,049/mtu WO₃ (US$1,500/mtu WO₃), while mine design and cut-off grade selection were developed using a conservative tungsten price assumption of $900/mtu WO₃ (US$659/mtu WO₃). The Company is providing the additional metrics below to facilitate investor understanding of project capital intensity, cash flow generation and payback presentation.
For additional reference, the Company is presenting payback under two different measurement bases. The previously disclosed payback metrics were measured from the start of construction (SC), consistent with standard technical study practice. To facilitate comparison with industry benchmarks, the Company is also providing indicative payback measured from the commencement of commercial production (CCP).
Table 1 - Economic Results (After-Tax)
ScenarioPrice1NPV (8%)2IRR3Payback SC4Payback CCP4
Medium$1,365/mtu
(USD $1,000/mtu)$473.4M
(USD $346.6M)48.8%2.2 years4.2 years
Base$962/mtu
(USD $704/mtu)$182.7M
(USD $134.0M)27.2%3.8 years5.8 years
High$2,049/mtu
(USD $1,500/mtu)$963.8M
(USD $706.4M)78.4%1.2 years3.2 years
Notes:
Prices based on Argus Media Group price forecasts. Canadian dollar (CAD) equivalents calculated used a foreign exchange rate of CAD $1.3658/USD.
NPV is a Non-GAAP measure; see notes below for additional information regarding NPV. M = million.
IRR is a Non-GAAP measure; see notes below for additional information regarding IRR.
Payback is a Non-GAAP measure. see notes below for additional information regarding payback.
Payback measured from the start of construction reflects recovery of initial capital over the full development and operating timeline, while payback measured from the start of commercial production excludes the construction phase and is presented for comparative reference only.
The results highlight significant sensitivity to tungsten price while maintaining positive economics under conservative long-term assumptions.
In the Base Case scenario, tungsten (WO₃) represents approximately 96% of project NPV, with minor contributions from copper (~3%) and tin (<1%), based on NSR contribution. This highlights that the Borralha Project economics are overwhelmingly driven by tungsten.
For reference, current reported tungsten market prices remain materially above the US$1,000 per mtu sensitivity case presented in the PEA, reaching approximately $2,998 per mtu (US$2,195 per mtu) as of March 6, 2026 (Source: Fastmarkets).
Mineral Resource Estimate
This initial PEA is based on the updated Mineral Resource Estimate ("MRE" or "2025 MRE") for the Santa Helena Breccia, which were presented in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") in the Company's current technical report on Borralha (the "Technical Report") entitled "Technical Report on the Borralha Property, Parish of Salto, District of Vila Real, Portugal", dated effective December 30, 2025, which is published on the Company's website at www.alliedcritical.com and under its profile on SEDAR+ at www.sedarplus.ca.
Under the 2025 MRE, the Santa Helena Breccia has been tested by 41 drill holes and surface trenching over approximately 400 meters of strike length and to depths exceeding 350 meters below surface. Mineralization remains open along strike and at depth. The cut-off grade of 0.09% WO3was selected based on reasonable prospects for eventual economic extraction under conceptual underground mining and gravity-dominant processing assumptions, including a very conservative tungsten price of USD$ 550/mtu WO₃ and assumed recovery of approximately 80% (for MRE cut-off determination only).
Table 2 -2025 MRE for Borralha (see also Technical Report for further details)
ClasificationTonnes (Mt)Grade (% WO3)
Measured + Indicated13.00.21
Inferred7.70.18
Initial Capital Allocation and Operational Costs
The Borralha PEA estimates initial capital7 of approximately US$91 million, with sustaining capital8 of approximately US$87 million and total life-of-mine capital9 of approximately US$178 million. The initial capital requirement reflects a compact project design integrating underground mine development, process plant construction and site infrastructure.
Table 3 - Initial Capital Costs
CategoryCAD$M*US$M
Underground development21.615.8
Processing plant23.116.9
Paste backfill plant5.94.3
Surface infrastructure6.74.9
Power connection9.87.2
EPCM / indirect costs**16.412.0
Contingency6.04.4
Tax incentives34.325.1
Subtotal Initial Capital123.791.5
*Canadian dollar (CAD) equivalents calculated used a foreign exchange rate of CAD $1.3658/USD.
**EPCM = Engineering, Procurement, and Construction Management.
Certain development expenditures may also qualify for applicable Portuguese investment tax incentives, which could partially offset initial capital expenditures.
Table 4 - Operating Cost10 Breakdown
Cost CategoryUS$/t Processed
Mining41.2
Processing13.2
G&A5.0
Transport0.02
TC/RC*0.51
Total Operating Cost**59.3
*TC/RC = Treatment Changes and Refining Charges. These are fees paid by mining companies to smelters to process raw material concentrate into refined metal.
**Operating costs for life-of-mine used for mine design average approximately US$49/t processed, based on the Sub-Level Long Hole Stoping (SLOS) mining method. Limited areas may utilize Drift & Fill mining, which carries higher unit costs. In the economic model, operating costs are expressed in nominal US dollars and escalated annually for inflation, resulting in an average life of mine operating cost of approximately US$59/t processed, including transportation and treatment/refining charges.
Concentrate Marketing Assumptions
The PEA assumes production of a marketable tungsten concentrate grading approximately 65% WO₃ using a gravity-dominant flowsheet. Concentrate pricing assumptions are based on industry-standard tungsten concentrate marketing structures, incorporating typical 80% payability terms and treatment charges applicable to the tungsten market.
The Project benefits from relatively clean mineralogy dominated by wolframite, which generally reduces impurity-related penalties relative to more complex tungsten concentrates.
Capital Efficiency
The relatively modest initial capital requirement reflects several favourable project characteristics, including:
compact underground mining footprint
gravity-dominant processing flowsheet
access to regional infrastructure including grid power
limited earthworks due to site topography
moderate plant throughput of 1.4 million tonnes per annum (Mtpa) of mineralized material
potential Portuguese investment incentives
These factors contribute to a capital-efficient development scenario compared with many global tungsten projects.
Simplified Annual Cash Flow Metrics
The initial Borralha mine plan is expected to generate strong annual cash flow11 supported by life-of-mine average production of approximately 1,708 tonnes WO₃ per annum, a nominal processing rate of 1.4 Mtpa, and an average mill feed grade of approximately 0.20% WO₃.
Table 5 - Cash-Flow11 Table
Cash Flow MetricBase Case
US$704/mtu WO₃Medium Case
US$1,000/mtu WO₃High Case
US$1,500/mtu WO₃
Average annual revenue131,749184,886274,686
Average annual EBITDA53,374104,101189,860
Average annual pre-tax operating cash flow40,40591,132176,890
Average annual free cash flow35,81570,493128,785
Life-of-mine revenue1,449,2342,033,7473,021,554
Life-of-mine free cash flow393,973775,4281,416,640
Infrastructure and Site Requirements
The Borralha Project benefits from favourable site conditions and access to existing regional infrastructure, supporting a capital-efficient development.
Surface infrastructure has been designed to concentrate industrial and administrative facilities within a compact footprint, minimizing environmental disturbance while ensuring operational efficiency. The process plant, paste backfill facility, workshops, administrative buildings and support infrastructure will be located on a centralized platform adjacent to the orebody.
Access to the site will utilize existing regional roads connected to the municipal road CM1025-2. Dedicated routes for light and heavy vehicles have been designed to ensure safe operations while minimizing earthworks and environmental impact.
A comprehensive water management system has been designed to support mining and processing operations. Water supply is expected to be sourced from local groundwater and surface water resources, with water recycling integrated into the process flowsheet. Three retention basins will provide operational water storage, sedimentation and environmental control.
Electrical power will be supplied through connection to the Portuguese national grid via a planned 60 kV overhead line linking the Borralha substation to the SE Frades (REN) substation over approximately 6.5 km. The design complies with applicable national standards and incorporates environmental protection measures.
The project infrastructure design integrates processing, backfill, water management and power supply systems to support efficient underground mining operations while minimizing environmental impact.
Key Infrastructure Advantages
Grid power connection (60 kV line - 6.5 km)
Local groundwater and surface water available for operations
Existing regional road access to site
Compact site layout minimizing environmental footprint
Paste backfill and water recycling integrated into plant design
Ongoing Growth Strategy
The current initial PEA is based only on the Santa Helena Breccia deposit and an initial 11-year production plan. The Company's fully funded 20,000-metre drill program is underway and is targeting:
expansion of the current Mineral Resource;
conversion of Inferred Mineral Resources into higher-confidence categories;
potential extension of mine life beyond the initial plan; and
evaluation of throughput optimization and future project scale growth.
The Company intends to continue advancing Borralha through additional drilling, engineering optimization, metallurgical refinement, geotechnical and hydrogeological studies, and progression toward the next stage of technical study.
Qualified Persons
The scientific and technical information contained in this news release has been reviewed and approved by the following Qualified Persons, as defined under NI 43-101:
J. Douglas Blanchflower, P.Geo.
Mr. Blanchflower is an independent Qualified Person under NI 43-101 and was retained by Allied Critical Metals Inc. to prepare the NI 43-101 Technical Report dated effective December 30, 2025. He has overall responsibility for the 2025 MRE and the Technical Report. Mr. Blanchflower is a Registered Professional Geoscientist in good standing with the Association of Professional Engineers and Geoscientists of British Columbia (No. 19086) and has more than five decades of experience in mineral exploration, resource estimation, and technical reporting. Mr. Blanchflower has reviewed and approved the scientific and technical information in this news release relating to the mineral resource estimate.
David Castro López, BSc, MIMMM, QMR
Mr. Castro López is a Mining Engineer and a Professional Member (MIMMM #685484) and Qualified for Minerals Reporting (QMR) of the Institute of Materials, Minerals and Mining (IOM3). He is independent of the Company and the Borralha Project. Mr. Castro López contributed to the metallurgical review and process design considerations supporting the PEA and takes responsibility for the metallurgical and mineral processing information contained herein. Mr. López has reviewed and approved the scientific and technical information in this news release relating to the metallurgical and mineral processing information contained herein.
Miguel Cabal, EurGeol, Licensed Geologist
Mr. Cabal is a licensed geologist with the European Federation of Geologists (EuroGeol #1439) with over 28 years of experience in mineral exploration, resource evaluation and mine development. He is Managing Director of Geomates (Spain) and has contributed to multiple NI 43-101 and JORC-compliant technical reports, including PEA, PFS and feasibility studies. Mr. Cabal is independent of Allied Critical Metals Inc. and the Borralha Project and has reviewed and approved the mining and economic components of the PEA. Mr. Cabal has reviewed and approved the scientific and technical information in this news release relating to the mining and economic components of this news release.
Vítor Arezes, BSc, MIMMM, QMR
Mr. Arezes is Vice President Exploration of Allied Critical Metals Inc. and a Qualified Person under NI 43-101. He is not independent of the Company due to his role as an officer. Mr. Arezes has extensive experience in tungsten and polymetallic mineral systems and has conducted multiple site visits to the Borralha Project, including during the 2025 drilling campaign. He contributed to geological interpretation, exploration oversight, and technical review supporting the PEA. He is a member of the Institute of Materials, Minerals and Mining (MIMMM #703197) and a Qualified Mineral Resources and Ore Reserves Professional (QMR), and by reason of education, professional experience, and accreditation, meets the definition of a Qualified Person as defined in NI 43-101. Mr. Arezes has reviewed and approved all of the scientific and technical information in this news release.
About Allied Critical Metals Inc.
Allied Critical Metals Inc. is a Canadian-based mining company focused on the advancement and revitalization of its 100%-owned Borralha Tungsten Project and the Vila Verde Tungsten Project in northern Portugal.
The Borralha Project is one of the largest undeveloped tungsten resources within the European Union and benefits from a favourable Environmental Impact Declaration (DIA), positioning the Project for advancement toward feasibility and development. Vila Verde represents additional exploration upside within the same strategic jurisdiction.
Tungsten has been designated a critical raw material by the United States and the European Union due to its strategic importance in defense, aerospace, manufacturing, automotive, electronics and energy applications. Currently, China, Russia and North Korea account for approximately 87% of global tungsten supply and reserves, highlighting the importance of secure western sources.
Further details regarding the Borralha Project are available in the Company's NI 43-101 Technical Report dated December 30, 2025, filed on SEDAR+ at www.sedarplus.ca and on the Company's website at www.alliedcritical.com.
ON BEHALF OF THE BOARD OF DIRECTORS
"Roy Bonnell"
CEO and Director
Additional information is also available by contacting the Company:
Dave Burwell
Vice President, Corporate Development
daveb@alliedcritical.com
Tel:403-410-7907
Toll Free: 1-800-221-0915
Please also visit our website at www.alliedcritical.com.
Also visit us at:
LinkedIn: https://www.linkedin.com/company/allied-critical-metals-inc/
X: https://x.com/@alliedcritical/
Facebook: https://www.facebook.com/alliedcriticalmetals/
Instagram: https://www.instagram.com/alliedcriticalmetals/
The Canadian Securities Exchange does not accept responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding Forward-Looking Information
This news release contains "forward-looking information" within the meaning of applicable Canadian securities laws ("FLI"). FLI in this release includes, without limitation, statements regarding: (A) the PEA results and economic indicators (e.g., NPV, IRR, payback and related sensitivities); (B) the conceptual mine plan and operating framework (mining approach, processing rates, production profiles, cost ranges and schedules); (C) the technical basis and process assumptions (cut-off approach, flowsheet concept and anticipated concentrate specifications); (D) the status and trajectory of permitting and approvals, infrastructure access and other site requirements; (E) market-related assumptions and the Project's sensitivity and leverage to commodity pricing; (F) growth, conversion and expansion opportunities, including planned drilling and other technical programs; (G) the anticipated sequence of future studies, potential financing pathways and indicative timelines; and (H) the Project's strategic positioning relative to regional and policy objectives. Such FLI is identified by, among other things, words such as "plans", "expects", "is expected", "aims", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", "potential", "target", "opportunity", "may", "could", "would", "might", "will" and similar terminology, as well as statements regarding outcomes that "will", "should" or "would" occur.
Earlier from Allied Critical Metals Inc.
More technical studies releases
- Oceanic Iron Ore CEO Chris Batalha Talks About the Hopes Advance Re-Scoped PEA Oceanic Iron Ore Corp. (FEO.V),
- Bravada Gold Files PEA for Wind Mountain Gold-Silver Project Bravada Gold Corporation (BVA.V),
- DLP Resources Files NI 43-101 Technical Report for the Aurora PEA DLP Resources Inc. (DLP.V),